Part I Managing Processes
Total crash costs = $1450
To use OM Explorer for this problem, you need to modify the input data a little.
The problem already gives the cost to crash per week for each activity. Since
OM Explorer assumes it must calculate these values, multiply the number of
weeks the activity can be crashed by the cost per week given in the problem
statement, e.g., for activity B, $250(3) = $750. The input sheet and the resulting
crash schedule should look like the exhibits below.
Solver – Crashing
Enter data in yellow shaded areas.
Indirect cost 1,600$ per week
Penalty cost 1,200$ per week after week 12
Activity
Crash Time Crash Cost Precedence 1 Precedence 2 Precedence 3 Precedence 4
a 7 0 6 200
b12 0 9 750
c 7 0 6 250 a
d 6 0 5 300 a
e 1 0 1 0 b
f 1 0 1 0 c d
g 3 0 1 400 d e
(Reduction in Time Periods)
17 400 400 27,200 06,000 33,600 1 1
16 450 850 25,600 04,800 31,250 1 1 2
15 600 1,450 24,000 03,600 29,050 1 1 1 2 1
13. Advanced Tech
a. The AON diagram, with all task durations at Normal Time, for the project is:
Start
A
6
F
2
B
4
C
3E
6
G
4
D
2
H
4
Finish
The critical path is A-C-E-G-H and the project duration is 23 days.
b. The computation of minimum-cost schedule is provided in the following output
from POM for Windows software.