26 CHAPTER 3 PRO J E C T MA N A G E M E N T
tI = 30
6.67*
44.44
tJ = 10
0.67
0.44
tK = 0
0.10
0.00
44.44
tI = 30
6.67*
44.44
tJ = 10
0.67
0.44
tK = 0
0.10
0.00
44.44
CASE STUDY
SOUTHWESTERN UNIVERSITY: A
1.
Standard deviation of critical path = 17.87 days
2. P (Completion < 270 days) = P(t 270)
−
= = =
270 260 0.56 0.712 71.2%
P Z P Z
3. Crash to 250 days and to 240 days
*Rounded to zero from 0.1
To crash to 250 days (from the current 260 days), select A at
$1,500/day 10 days = $15,000.
1. Construction project network:
2. The critical path is Activities 1–3–5–6–8–10–11–12–14–16–
17–19–20–21. The project length is 47 months—about four
years from start to finish.
3. Building a hospital is much more complex than an office build-
ing for several reasons. In this case, hundreds of “users” of the
new building had extensive input. Second, the design of the new
layout (circular, pod design) is somewhat radical compared to
4. Since there were 13 months of planning prior to the proposal/
review stage (listed as Activity 1) and the project then took
47 months (for a total of 60 months), 22% of the time was
spent in planning.