building at an estimated cost of $2,750,000. The issuance of
11. On March 31, 2091, the Province government transferred $250,000 to
12. On April 1, 2091, $2,500,000 in 10 percent general obligation
long–term bonds were issued for $2,580,000. The premium of $80,000 was
13. On June 1, 2091, the school building contract was awarded to the
14. On November 30, 2091, the progress billings of $1,250,000 for the
school building were received from the contractor and $ 850,000 was
15. The Board of the Bureau of Electricity and Water approved the
16. On July 1, 2091, the office building contract was signed in the
17. On October 30, 2091, construction was completed and $632,500 was
paid on the contract. The remaining portion ($ 232,500) will be paid
18. At the end of November, ground transportation units were ordered