Chapter 05 Strategic Capacity Planning for Products and Services
511
8.
Given:
Source
FC
v
Internal 1
$200,000
$17
Internal 2
240,000
14
Vendor A
20 up to 30,000 units
Vendor B
22 for 1 to 1,000; 18 each if larger amount
Vendor C
21 for 1 to 1,000; 19 each for additional units
a.
TC for 20,000 units
200,000 + 17(20,000) = $540,000
240,000 + 14(20,000) = $520,000
20(20,000) = $400,000
Vend B: 18(10,000) = $180,000
18(20,000) = $360,000
21,000 + 19(19,000) = $382,000
b. Given:
Cost functions for each alternative:
Internal 1: $200,000 + $17Q
Internal 2: $240,000 + $14Q
Vendor A: $20Q (Q ≤ 30,000)
Vendor B: $22Q (Q ≤ 1,000) $18Q for all units when Q > 1,000
Vendor C: $21Q (Q ≤ 1,000) $21Q + $19(Q – 1,000) when Q > 1,000
First, we analyze the range of 1 – 1,000 units:
Vendor A exhibits lower total cost over this range than do Vendor B and Vendor C; therefore,
we can eliminate Vendors B & C from consideration for this range.
Next, we could graph the costs functions of the remaining three options for the range of 1
Chapter 05 Strategic Capacity Planning for Products and Services
512
Education.
Second, we analyze the range of 1,001 units or more to determine the total costs if we purchase >
1,000 units:
Total Cost Functions (when purchasing 1,001 units or more):
Internal 1: $200,000 + $17Q
Internal 2: $240,000 + $14Q
Vendor A: $20Q (≤ 30,000 units)
Vendor B: $18Q
We can plot these costs functions on a graph as shown in the Excel chart below:
Int. 1
Int. 2
Vend A
0
50,000
100,000
150,000
200,000
250,000
300,000
0 1000
$
Units
Chapter 05 Strategic Capacity Planning for Products and Services
Set the two cost functions equal and solve for Q:
$18Q = $240,000 + $14Q
$18Q – $14Q = $240,000
$4Q = $240,000
Q = $240,000/$40
1 1,000 units Prefer Vendor A
1,001 59,999 units Prefer Vendor B
60,000 units Indifferent between Vendor B & Internal 2
> 60,000 units Prefer Internal 2
Note: Internal 1 and Vendor C are never best.
Int. 1
Vend B
Int. 2
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
0 10000 20000 30000 40000 50000 60000 70000
$
Units
Chapter 05 Strategic Capacity Planning for Products and Services
9. Given: Actual output will be 225 per day per cell. 240 working days/year. Projected annual demand =
150,000 within 2 years.
10. Given: Our objective is to select one type of machine to purchase. We are given the data below:
a. Number of machines of each type needed if the machines will operate 60 minutes per hour, 8
hours per day, 250 days per year.
Using Machine Type 1:
Total = 228,000 min.
Number of Machine Type 1 Needed = processing time needed / processing time capacity per unit
= 228,000 / 120,000 = 1.9 = 2 machines (round up)
Capacity = 2 x 120,000 minutes = 240,000 minutes
Capacity cushion = 240,000 228,000 = 12,000 minutes
Product 003: 18,000 x 3 min. = 54,000 min.
Total = 216,000 min.
Number of Machine Type 2 Needed = processing time needed / processing time capacity per unit
= 216,000 / 120,000 = 1.8 = 2 machines (round up)
Capacity = 2 x 120,000 minutes = 240,000 minutes
Machine Type
Purchasing
Cost/Machine
1
$10,000
2
$14,000
001
12,000
4
6
002
10,000
9
9
003
18,000
5
3
Chapter 05 Strategic Capacity Planning for Products and Services
516
Education.
b. Given: Operating Costs: A = $10/hour/machine; B = $11/hour/machine; C =
$12/hour/machine.
Total cost for each type of machine:
A (2): 186,000 min. / 60 min./hour = 3,100.00 hrs. x $10 = $31,000 + $80,000 = $111,000
B (2): 208,000 min. / 60 min./hour = 3,466.67 hrs. x $11 = $38,133 + $60,000 = $98,133
C(1): 122,000 min. / 60 min./hour = 2,033.33 hrs. x $12 = $24,400 + $80,000 = $104,400
12. Given: R = $45 per customer, v = $20 per customer, each machine can process 100 customers per
day, fixed cost for one machine = $2,000 per day total; and fixed cost for two machines = $3,800 per
day total.
a. FC Range
vR
FC
QBEP
517
Education.
13. Given: R = $5.95/car, v = $3/car, Fixed Cost for one line = $6,000/month, Fixed Cost for two lines =
$10,500/month, each line can process 15 cars/hour, & the car wash is open 300 hours/month.
Determine the break-even for each option:
To do this, we will need to convert fixed costs per month to fixed costs per hour.
One line fixed cost per hour = $6,000/300 = $20
00.3$95.5$
R
Two Lines:
cars 86.11
00.3$95.5$
35$
R
v
FC
QBEP
If demand averages between 14 and 18 cars an hour, either option would break even. Therefore, we
Volume
No. of Lines Used
Net Profit per Hour
14
1
$21.30 = 14 (5.95 3) 20
15
1
24.25 = 15 (5.95 3) 20
16
1
24.25 = 15 (5.95 3) 20
17
1
24.25 = 15 (5.95 3) 20
18
1
24.25 = 15 (5.95 3) 20
Volume
No. of Lines Used
Net Profit per Hour
14
2
$6.30 = 14 (5.95 3) 35
15
2
9.25 = 15 (5.95 3) 35
16
2
12.20 = 16 (5.95 3) 35
17
2
15.15 = 17 (5.95 3) 35
18
2
18.10 = 18 (5.95 3) 35
Conclusion: Choose one line. Net profit per hour always is higher using
one line for the given demand range of 14 to 18 cars per hour.
Chapter 05 Strategic Capacity Planning for Products and Services
14. Given : We have a 4-step process with the following effective capacity for each operation:
Operation 1 = 12/hr, Operation 2 = 15/hr, Operation 3 = 11/hr, Operation 4 = 14/hr.
a. The capacity of the process is determined by the operation with the lowest effective capacity:
Operation 3 = 11/hr.
Operation 1 = 12/hr, Operation 2 = 15/hr, Operation 3 = 12.1/hr, Operation 4 = 14/hr.
The capacity of the process is determined by the operation with the lowest effective capacity:
Operation 1 = 12/hr. Increase in capacity = 1/hr (12/hr 11/hr).
Conclusion: Select Option 3. Increasing the capacity of Operation 3 by 10% yields the
greatest increase in process capacity (1/hr).
15. Given: Two parallel lines feed their combined output to Operation 7.
Upper Line Capacities: Operation 1 = 18/hr, Operation 2 = 15/hr, Operation 3 = 16/hr.
Lower Line Capacities: Operation 4 = 17/hr, Operation 5 = 15/hr, Operation 6 = 17/hr.
Capacity of Operation 7 = 20/hr. Capacity of Operation 8 = 24/hr.
519
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
b. Given: The capacity of one operation could be increased.
Process capacity is limited by Operation 7; therefore, increase the capacity of Operation 7 by
4 units/hour from 20 units/hour to 24 units/hour at which time Operation 8 also becomes a
bottleneck.
16. Given: Three parallel lines feed their combined output to Operation 10.
Upper Line Capacities: Operation 1 = 22/hr, Operation 2 = 17/hr, Operation 3 = 18/hr.
Middle Line Capacities: Operation 4 = 20/hr, Operation 5 = 18/hr, Operation 6 = 18/hr.
17. Given: Two parallel lines feed their combined output to Operation 7.
Upper Line Capacities: Operation 1 = 15/hr, Operation 2 = 10/hr, Operation 3 = 20/hr.
Lower Line Capacities: Operation 4 = 5/hr, Operation 5 = 8/hr, Operation 6 = 12/hr.
Capacity of Operation 7 = 34/hr. Capacity of Operation 8 = 30/hr.
Conclusion: Increase the capacity of Operation 2 by 5/hr. The resulting process capacity
would be 20/hr.