Choose one activity on each path to crash:
Activity B should be shortened 1 week because it has the lowest crashing cost ($7) on
Path A-B-C.
Activity G should be shortened 1 week because it has the lowest crashing cost ($11) on
Path F-G-H.
Path A-B-C now will be 13 weeks as shown below.
Critical paths are A-B-C, D-E-C, and F-G-H.
Rank critical activities according to crash costs:
on Path D-E-C. The combined crashing cost would be $8 + $8 = $16. However, Activity
C is on both paths and could be crashed for $14.
Activity C should be shortened 1 week at a crashing cost of $14.
Activity H should be shortened 1 week because it has the lowest crashing cost ($12) on
Path F-G-H.