Chapter 12 – MRP and ERP
12–41
12. Given:
200 carts must be ready at the beginning of week 8. The product structure tree, assembly time
chart, and inventory information are shown in the solutions below:
a. Product structure tree:
Assembly Time Chart
Chapter 12 – MRP and ERP
c. Develop a material requirements plan that will provide 200 golf carts by week 8 assuming
lot-for-lot ordering.
Master
Schedule for:
Golf Cart
Golf Cart LT = 1
Lot size: Lot-for-Lot
Top LT = 1
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 7) = Planned-Order Releases of 200 Golf Carts * 1 = 200.
Supports(4) LT = 1
Lot size: Lot-for-Lot
12–43
12. c. (continued)
Cover LT = 1
Lot size: Lot-for-Lot
Base LT = 1
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 7) = Planned-Order Releases of 200 Golf Carts * 1 = 200.
Motor LT = 2
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 1 = 180.
12–44
12. c. (Continued)
Body LT = 3
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 1 = 180.
Seats(2) LT = 2
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 2 = 360.
Frame LT = 1
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 1 = 130.
12–45
12. c. (Continued)
Controls LT = 1
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 1 = 130.
Wheel Assemblies(4) LT = 1
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 4 = 520.
Scheduled receipts
Projected on hand
Net requirements
100
100
Planned-order receipts
100
100
Planned-order releases
100
100
Gross requirements
100
100
100
Net requirements
100
100
Planned-order receipts
100
100
13. Given:
Refer back to Problem 12. The revised plan calls for 100 golf carts to be available at the start of
week 6, 100 at the start of week 8, and 100 at the start of week 9.
a. Develop a master schedule for this revised plan.
Master
Schedule for:
Golf Carts
b. Determine the timing and quantities for orders for tops and bases.
Golf Cart LT = 1
Lot size: Lot-for-Lot
Chapter 12 – MRP and ERP
c. The firm’s capacity limits the assembly of bases to 50 units per week. Revise the plan, but
Planned Order-Receipts (week 7) = 100
Planned Order-Receipts (week 5) = 80
Given the capacity limit of 50 per week, we could divide the Planned-Order Receipts as
follows:
Week 8 (100): Week 7 (50) & Week 8 (50)
schedule them automatically.
Master
Schedule for:
Golf Carts
Chapter 12 – MRP and ERP
12–49
Education.
Top Blade Assembly
LT = 1
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 5) = Planned-Order Releases of 600 Scissors * 1 = 600.
Screw LT = 1
Lot size: Lot-for-Lot
Straight Blade LT = 1
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 4) = Planned-Order Releases of 600 Bottom Blade Assembly * 1 =
600.
Chapter 12 – MRP and ERP
12–50
Education.
Straight Plastic Grip
LT = 2
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 4) = Planned-Order Releases of 600 Bottom Blade Assembly * 1 =
600.
Bent Blade LT = 1
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 4) = Planned-Order Releases of 560 Top Blade Assembly * 1 = 560.
Bent Plastic Grip LT = 2
Lot size: Lot-for-Lot
Notes: Gross Requirements (week 4) = Planned-Order Releases of 560 Top Blade Assembly * 1 = 560.