Two Examples
Two examples, the Fuel Tank and the Headliner, can be used to illustrate how
the successful application of the ESIDS helped Deere and its supplier.
The Fuel Tank Example
The fuel tank on the skid-steer loader is a component that can be mapped onto
the early supplier integration decision scheme as follows:
• Percent of final product value: low = 2 percent
• Costs of production tooling: high
• Impact on final product reliability: low
• Time to do production Tooling: high (typically 12-14 weeks)
Two out of the four criteria on the Early Supplier Integration Decision Scheme,
suggest that the supplier should be integrated in the early phases of the skid-
steer loader development process. Once the supplier was selected, Deere
engaged in a close collaboration with the supplier to establish a climate of
trust. This was a prerequisite for the supplier to openly share sensitive cost
data with Deere.
The collaboration with the supplier was key to the meeting of the project goals.
For example, in order to assess product quality, Deere required that tank
prototypes be manufactured with the same process they would have gone
through in volume production. This required metal dies to be cut.
Unfortunately, after six months of work, the fuel tank was still 30-40 percent
above target cost, so that many engineering design changes would likely be
required to comply with target cost requirements. Given the 12-14 weeks lead-
time for the fuel tank die cutting, this situation was seriously threatening
Deere’s capability to meet the 24-month deadline. By collaborating with the
fuel tank supplier it was possible to reduce the die cutting lead-time from the
typical 12-14 weeks to just 7 weeks. This successful collaboration ensured on-
time and on-cost fuel tank design release.
This supplier was integrated by multiple methods. For example, the suppliers’
design personnel regularly visited the design team at the Knoxville facility every
two weeks to discuss advances in design, as well as engineering changes
needed to meet cost targets. Moreover, Deere and the supplier shared CAD
drawings and files through a shared database to ensure timely exchange and
alignment of product design information.