Latest Finish (LF) – the latest an activity can finish and still ensure that the project can be
completed on its scheduled time.
6. The management significance of the critical path is that it constrains the completion date
of the project since it is the longest path of activity times from the start to the end of the
network. As a result, activities on the critical path should be intensively managed to avoid
slippage. Other activities, not on the critical path, can be allowed to slip somewhat, up to
their amount of slack, without affecting the project completion date.
7. The Gantt chart indicates activity duration; when each activity is scheduled to begin and
when it will be completed. The chart can be used for less complex projects and when
activity times are constant – it is easy to use and easily understood. The output of network
methods can also be shown in Gantt chart format.
8. Since cost, performance and schedule are three conflicting objectives of a project, tradeoffs
among them must constantly be made in the course of project management. For example,
to design and plant a unique and exquisite garden will require more investments in time
and money than planting an ordinary garden. In this case, superior performance cannot be
achieved with minimal cost and within a short period of time.
9. Forward and backward passes are needed for the calculation of early start, early finish, late
start, and late finish times for activities. This information in turn can be used to identify
the critical path, slack times and project completion time.
10. Earliest Start, ES – earliest time an activity can start based on completion of all predecessor
activities
Latest Start, LS – latest time an activity can start and still achieve its latest finish time
Earliest Finish, EF – earliest time an activity can be completed given that it starts at its
11. There are three statistical assumptions. The first assumption is that the random times of
activities are independent. That means the time duration of one activity does not affect the
time duration of any other activity. The second assumption is that the total time of
completion of the project is normally distributed. The third assumption is that the activity
times are distributed according to the Beta distribution.
In most cases the duration of one activity may not affect another activity. But, there may