(M) 13. The critical path is the path in the network with the greatest amount of risk.
(E) 14. If the optimistic time for an activity is 6 weeks, the pessimistic time is 24 weeks and
the most likely time is 12 weeks, then the expected duration is:
(E) 15. Which of the following schedule compression techniques usually requires adding more
resources to each work package that is being compressed?
(M) 16. In which of the following schedule compression techniques is the cost of rework
usually the greatest?
(M) 17. Which of the following schedule compression techniques is often the lowest risk and
with the added benefit of lowering the cost?
(E) 18. Smoothing out project resources from period to period is called