72) A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task
involves use of a ruler, square, and portable electric saw to mark and cut the “notch” in a rafter (a
standard carpentry task of home construction). In a preliminary study, he observed one of his workers
performing this task five times. The observations were made in an air-conditioned, well-lit training
facility, at ground level, with all tools and equipment clean and readily available.
a. What is the actual average time for this task?
b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for
adequately trained workers?
c. What is standard time for this task if allowances sum to 14%?
d. If the analyst then thought more carefully about his experiment and decided that the allowances
needed to be increased to match the real (outside, not air-conditioned) work environment, and that the
proper allowance was not 14% but 20%, what is the revised standard time?
73) A task involves positioning two metal parts with a rubber gasket sandwiched between them, inserting
two bolts into predrilled holes, threading a nut onto each bolt, and tightening each bolt with a pneumatic
wrench. In a preliminary study, the manager observed one of his workers performing this task five times.
The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools
and equipment clean and readily available.
a. What is the average observed time for this task?
b. What is the normal time for this task if the employee worked at a 10% slower pace than is typical for
adequately trained workers?
c. What is standard time for this task if allowances sum to 14%?