103. Atlantic Manufacturing Company uses process costing. All materials are added at the
beginning of the process. The normal spoilage rate is calculated as 10% of good units completed.
The cost of the beginning work–in-process in the Month of May is $3,000,000, including
$1,600,000 of input of materials, 100,000 units, and $1,400,000 for conversion costs. The
beginning work-in–process is 70% complete.
During May, the input includes $7,400,000 for materials, 800,000 units started and $4,190,000 for
conversion costs. There were 700,000 good units finished. In addition, the ending work–in–
process in May is 100,000 units with 60% complete. The abnormal spoilage is 30,000 units. All
spoilage occurred when all processing was complete, at the final inspection.
Required:
Use the weighted-average method to calculate:
(a) The dollar value of abnormal spoilage.
(b) The cost of the good units finished.
(c) The cost of ending work–in-process inventory.