to unanticipated price increases. What is the total amount of Construction Expenses that
Seasons will recognize for the year ended December 31, 2019?
a. €13,500,000
b. €7,875,000
c. €7,987,500
d. €8,175,000
Seasons Construction is constructing an office building under contract for Cannon Company and
uses the percentage–of-completion method. The contract calls for progress billings and payments
of €1,550,000 each quarter. The total contract price is €18,600,000 and Seasons estimates total
costs of €17,750,000. Seasons estimates that the building will take 3 years to complete, and
commences construction on January 2, 2018.
*102. At December 31, 2019, Seasons Construction estimates that it is 75% complete with the
building; however, the estimate of total costs to be incurred has risen to €18,000,000 due
to unanticipated price increases. What is reported in the statement of financial position at
December 31, 2019 for Seasons as the difference between the Construction in Process
and the Billings on Construction in Process accounts, and is it a debit or a credit?
Difference between the accounts Debit/Credit
a. €4,225,000 Credit
b. €1,550,000 Debit
c. €1,100,000 Debit d. €1,550,000
Credit
Seasons Construction is constructing an office building under contract for Cannon Company and
uses the percentage–of-completion method. The contract calls for progress billings and payments
of €1,550,000 each quarter. The total contract price is €18,600,000 and Seasons estimates total
costs of $17,750,000. Seasons estimates that the building will take 3 years to complete, and
commences construction on January 2, 2018.
*103. Seasons Construction completes the remaining 25% of the building construction on
December 31, 2020, as scheduled. At that time the total costs of construction are
€18,750,000. What is the total amount of Revenue from Long-Term Contracts and
Construction Expenses that Seasons will recognize for the year ended December 31,
2020?
Revenue Expenses
a. €18,600,000 €18,750,000
b. €4,650,000 € 4,687,500
c. €4,650,000 € 5,250,000
d. €4,687,500 € 4,687,500
Cooper Construction Company had a contract starting April 2018, to construct a €24,000,000
building that is expected to be completed in September 2020, at an estimated cost of €22,000,000.
At the end of 2018, the costs to date were €10,120,000 and the estimated total costs to complete
had not changed. The progress billings during 2018 were €4,800,000 and the cash collected
during 2018 was €3,200,000. Cooper uses the percentage-of-completion method.