1. The McCoys had breached the contract by failing to exercise “due diligence” in securing a
mortgage commitment because they did not inquire about any other financing alternatives.
The Browns were entitled to retain the $127,000 deposit as liquidated damages. McCoy v.
Brown, 24 A.3d 597 (Conn. App.)
4. Yes. The court pointed out that all the conditions required for setting liquidated damages had
been met. The parties intended to establish liquidated damages prior to the breach since there
was a clause providing for them in the contract. Orr and Bolstridge admitted that damages
would be difficult to ascertain and the court found the amount reasonable. Since Orr and
Bolstridge kept the deposit they had elected to keep the liquidated damages as their damages
for breach and could not recover more. Orr v. Goodwin, 953 A.2d 1190 (N.H.)
5. No. The court said that the brothers did not show that they were ready, willing, and able to
furnish unencumbered title and provide closing documents as required by the contract. Since
they did not tender performance, it could not be said that Olympia breached the contract.
Neither party was ready to close on the contract as required. The brothers were not entitled
to the earnest money. Radkiewicz v. Radkiewicz, 818 N.E.2d 411 (Ill.App.)
9. The DelGrecos should recover the $1,500 they paid the architect and the $18,500 they paid
the second architect to correct the job. However, since Shewmake and Kelly had had to
spend $19,100 on the job which they had not been paid, the $20,000 the DelGrecos should
recover should be reduced by the $19,100 they still owed Shewmake and Kelly. The
DelGrecos should recover $900. Shewmake v. DelGreco, 926 So.2d 348 (Ala. Civ.App.)
Answers to Summary Cases for Part Two
(Page 144)
1. In order to be a third party beneficiary, En-Staff had to show that the contracting parties
intended to benefit it. The court said that the language of the contract clearly showed that the