CHAPTER 7
PROJECT MANAGEMENT
Internet Case Study: Southwestern University
1. The project network is shown below.
3. We can easily determine the optimal crashing schedule for this project by hand without having to resort
to LP. To crash to 250 days from the current 260 days, we crash activity A by 10 days at $1,500/day, for a