CHAPTER 7
PROJECT MANAGEMENT
Internet Case Study: Bay Community Hospital
1. The project network is shown below. Under the present situation, the project completion time is 10
2. If activity E on the critical path is reduced by one week using express truck, the completion time
3. The cost of air shipment ($750) and overtime ($600) increases the total project cost by $1,350.