Activity Pred Time EST EFT LST LFT Slack Critical?
B – 4.0 0.0 4.0 1.0 5.0 1.0 N
C A, B 3.0 4.0 7.0 5.0 8.0 1.0 N
E – 8.0 0.0 8.0 0.0 8.0 0.0 Y
Internet Case: Bay Community Hospital
Activity Pred Time EST EFT LST LFT Slack Critical?
A – 2.0 0.0 2.0 2.0 4.0 2.0 N
D B 4.0 4.0 8.0 4.0 8.0 0.0 Y
Internet Case: Bay Community Hospital