EST EFT LST LFT Slack Critical? Critical path =
A – 1.00 2.00 3.00 2.00 0.11 0.33 0.00 2.00 0.00 2.00 0.00 Y Project length = 35.50 days
B – 1.00 1.50 5.00 2.00 0.44 0.67 0.00 2.00 1.00 3.00 1.00 N Project variance = 0.6944
C A 0.50 1.00 1.50 1.00 0.03 0.17 2.00 3.00 2.00 3.00 0.00 Y Project std deviation = 0.8333 days
G E 2.00 2.00 2.00 2.00 0.00 0.00 5.00 7.00 7.00 9.00 2.00 N
I H 2.00 2.50 6.00 3.00 0.44 0.67 8.00 11.00 10.00 13.00 2.00 N
J E 1.00 3.00 5.00 3.00 0.44 0.67 5.00 8.00 5.00 8.00 0.00 Y
K D 2.00 2.00 2.00 2.00 0.00 0.00 4.00 6.00 6.00 8.00 2.00 N
L K, J 1.00 2.00 3.00 2.00 0.11 0.33 8.00 10.00 8.00 10.00 0.00 Y
M L 2.00 2.00 2.00 2.00 0.00 0.00 10.00 12.00 10.00 12.00 0.00 Y
N M 1.00 1.00 1.00 1.00 0.00 0.00 12.00 13.00 12.00 13.00 0.00 Y
O N 0.50 0.50 0.50 0.50 0.00 0.00 13.00 13.50 13.00 13.50 0.00 Y
P I 0.50 0.50 0.50 0.50 0.00 0.00 11.00 11.50 13.00 13.50 2.00 N
Q O, P 0.50 1.00 1.50 1.00 0.03 0.17 13.50 14.50 20.50 21.50 7.00 N
R Q 0.00 0.00 0.00 0.00 0.00 0.00 14.50 14.50 21.50 21.50 7.00 N
T S 3.00 0.00 0.00 14.50 17.50 14.50 17.50 0.00 Y
U T 2.00 0.00 0.00 17.50 19.50 17.50 19.50 0.00 Y
V U 2.00 0.00 0.00 19.50 21.50 19.50 21.50 0.00 Y
W R, V 3.00 0.00 0.00 21.50 24.50 21.50 24.50 0.00 Y
X W 1.00 0.00 0.00 24.50 25.50 24.50 25.50 0.00 Y
Y X 1.00 0.00 0.00 25.50 26.50 25.50 26.50 0.00 Y
Z Y 4.00 0.00 0.00 26.50 30.50 26.50 30.50 0.00 Y
AA Z 1.00 0.00 0.00 30.50 31.50 30.50 31.50 0.00 Y
Internet Case: Alpha Beta Gamma Record (Thrift Print)
A-C-E-J-L-M-N-O-S-T-
U-V-W-X-Y-Z-AA-BB
E C, B 2.00 2.00 2.00 2.00 0.00 0.00 3.00 5.00 3.00 5.00 0.00 Y
F C, B 1.00 1.00 1.00 1.00 0.00 0.00 3.00 4.00 8.00 9.00 5.00 N