Shipments:
From Job 1 Job 2 Job 3 Flow out Location Flow in Flow out Net flow Sign RHS
Acme 2250.0 3750.0 0.0 6000.0 Acme 0 6000 -6000 >= -6000
Flow in 2500.0 3750.0 4850.0 Job 1 2500 0.0 2500 =2500
From Job 1 Job 2 Job 3
Total cost = $52,200
To
Problem 5-13
To
Flow balance equations
Shipments:
From Job 1 Job 2 Job 3 Acme Flow out Location Flow in Flow out Net flow Sign RHS
Acme 2500.0 3750.0 0.0 0.0 6250.0 Acme 250.0 6250 -6000 >= -6000
Flow in 2500.0 3750.0 4850.0 250.0 Job 1 2500 02500 =2500
From Job 1 Job 2 Job 3 Acme
Total cost = $51,450
To
Flow balance equations