*** Problem Set Key — Do Not Post or Distribute ***
Chapter 3: Process Choice & Layout Decisions in Manufacturing & Services
Introduction to Operations & Supply Chain Management (Bozarth & Handfield, 3rd Edition)
DIRECTIONS To generate the key, put in the 4-digit number used when printing
off the original assignment.
75
Problem 1 Max Products is setting up an assembly line to produce
radio dog collars. The line will run 12 hours a day, and
will need to produce 400 collars a day. The various
tasks, along with their required times and immediate
predecessors, are shown below.
Task
G14 D
H22 D
Total 424 seconds
Problem 1 In the space below, calculate the takt time and the minimum number
of workstations for the line. Show your work.
Takt time = Available production time
Required output rate
KEY: Process Choice and Layout Decisions
*** KEY ***
Problem 2 Suppose that management ignores the takt time and minimum
workstation calculations in Problem 1, and decides to set
up four workstations, as follows:
Workstation 1: Activities A and C
Workstation 2: Activities B, D, E, G and H
In the space below, calculate the cycle time for this line, as well as the idle time
and percent idle time.
Workstation Total task time
1 119
2 125