Chapter 17 Project Management
1715
6. The network diagram is given in Problem 1, Part a.
For path 12471012, the 13 weeks required for 124 has been reduced to 12 weeks. On
path 12581012, the 12 weeks required for 125 has been increased to (about) 14 weeks
[12+(86)]. However, 12581012 is not along the critical path and has a slack of 7 weeks.
7. a.
6
4
g
i
f
d
b
h
b.
Activity
te
2
Expected
Duration
Std.
Dev.
24
Prob.
a
6
4/36
20.5
1.118
3.13
0.9991
b
8.5
9/36
21.5
1.344
1.86
0.9686
d
36/36
f
6
4/36
(21 20.5)
= .447 0.45
0.6736
g
3.5
25/36
1.118
h
4.17
1/36
i
6.83
9/36
(21 21.5)
1.344
0.9808
0.3557
= 2.065 2.07
0.7265
0.6736 x 0.3557 x 0.9808 = 0.235
2
5
c
e
a
Chapter 17 Project Management
1716
c. On the 8th day, the network could be reviewed as follows:
*Assume it is the beginning of the 8th day
1
3
8
6
f (6)
g (3.5)
Replace d by d and merge nodes (2) and (4) with (1).
d: te = 6: 2 = 4/36
7 days were used to complete activities a, b and one half of d. In the modified network:
Path
Expected Duration
from 8th day
Expected duration from
the start of the project
Variance
1.
ce
14.50
14.50 + 7 = 21.5
41/36
2.
dfg
3.
11
11 + 7 = 18
10/36
Path
Standard Dev.
Z24
Probability (24)
1.
ce
1.0672
24 21.5
= 2.343
.9904
0.9574
3.
1.0000
= 11.384
0.527
.9904(.9418)(1.0000) = .9328
Path
Z21
Probability (21)
1.
ce
21 21.5
1.0672
2.
dfg
21 22.5
= 1.567
0.0582
0.9574
3.
0.527
.3192 (.0582)(1.0000) = 0.0186
5
7
i (6.83)
h (4.17)
day
e (6.33)
c (8.17)
Chapter 17 Project Management
1717
d. Crash activities F, C, and G one day each for a total cost of $23,000. Decide if an additional
expenditure of $3,000 over budget would be worth the cost, or if it would be better to crash only
one day (Activity F for a cost of $7,000), or don’t crash at all.
8.
Path
Expected
Duration
Std. Dev.
Z16
Z15
Z13
A
10
1.1
5.45
4.55
2.73
C
12
1.
4
3
1
D
15
1.7
0.59
0
1.18
E
14
1.2
1.67
0.83
0.83
(a) Prob. (T 16) = 1 x 1 x 1 x 0.7224 x 0.9525 = 0.6881
9. Solution
Path
Expected
duration
Std. dev.
z
Probability
123
4 + 5 = 9
1.64
0.61
.7291
10. Solution
a.
Path
Expected
duration
Std. Dev.
z for 11 wk.
Probability
124
4 + 6 = 10
1.14
0.88
.8106
134
2.00
b.
Path
Expected
duration
Std. dev.
z for 12 wk.
Probability
124
4 + 6 = 10
1.14
1.75
.9599
134
0
B
1.414
5.66
4.95
3.54
Chapter 17 Project Management
1718
11. Project Management
a.
Path
Mean
Var.
Std. Dev.
z49
Prob.
z46
Prob.
124611
43
5.11
2.26
2.65
.996
1.33
.9082
12510911
46.83
1.25
1.118
1.94
.9738
0.74
.2296
Chapter 17 Project Management
1719
12.
Activity
Expected
Duration
Path
Mean
Variance
Path
Variance
Path Std.
Dev.
a
4.
16/36
d
8.
16/36
e
9.17
25/36
h
3.17
f
4.5
25/36
4.[a]
16/36
b
2.17
1/36
14.83
1.03
1.014
i
3.33
16/36
j
4.
4/36
k
5.33
16/36
c
8.17
26.17*
49/36
2.75
1.658
n
7.5
25/36
o
9.5
25/36
*critical path duration
h
d
a
g
f
e
End
Start
k
b
c
m
i
j
n
o
Chapter 17 Project Management
1720
Path
Mean
Std. Dev.
z27
Prob.
z26
Prob.
adeh
24.34
1.354
1.96
.9750
1.23
.8907
afg
15.5
1.258
9.14
1.0000
8.35
1.0000
13.
Activity
Duration (wk.)
first crash
second crash
1-2
5
$8 #2
$10
2-4
6
9
4-7
3
14 #3
15
1-3
3
9
11
3-4
7
8
9
1-5
5
10 #1
15
5-6
5
11 #2
13
6-7
5
12 #3
14
3
1
5
6
7
2
4
7
5
6
3
14.83
1.014
11.00
1.0000
cmno
26.17
1.658
.4602
Chapter 17 Project Management
1721
Path
Initial time
After first crash
After second crash
After third crash
1-2-4-7
14 wk.
14 wk.
13 wk.
12 wk.
First Crash
Second Crash
Third Crash
Activity Cost
1 – 5 $10
Activity Cost
2 – 4 $7
Activity Cost
4 – 7 $14
14.
G
15
3
N
11
12
Length after crashing N weeks
Path
N:
0
1
2
3
4
5
ABK
35
CEHP
44
43
42
42
42
40
CDGM
45
44
43
43
CEHN
47
46
45
45
45
44
CFIJP
49
48
47
46
45
44
B
14
A
12
K
9
M
C
Start
End
1-5-6-7
Chapter 17 Project Management
1722
15.
Weeks Crashed
Activity
1st week
2nd week
3rd week
1
2
3
4
5
6
12
$18 [2]
$22 [6]
$18
$22
57
30
30
35
15 [1]
20 [3]
1113
30 [4]
33 [5]
36
30
33
38
40
40
40
39
3
10
12
10
1213
26
14
10 [5]
15
25
10
46
8 [4]
13
8
12 [6]
1012
14
15
$15
$18
$25
$38
$43
$46
Weeks Crashed
Path
0
1
2
3
4
5
6
12571113
35 wk.
34
33
32
31
30
29
1391213
20
146101213
33
33
32
31
30
29
25
24
25
25
Chapter 17 Project Management
1723
Summary:
Project
Length
Cum. wk.
Shortened
Cum. Crash
Costs ($0000)
Indirect Costs
($000)
Total Cost
($000)
35
0
0
35(40) = 1,400
1,400
34
1
15
34(40) = 1,360
1,375
33
2
33
33(40) = 1,320
1,353
1,300
Total
Cost
($000)
1,400
32
3
58
32(40) = 1,280
1,338
31
4
96
31(40) = 1,240
1,336
29
6
29(40) = 1,160
1,345
Chapter 17 Project Management
1724
16.
Project duration = 39 wk
Project
length
Shorten
activity
Crash
cost
39 wk
0
38
Z
90
37
36
35
34
17. a. 18.5 (See table in part b.)
b.
Path
Expected Duration
Standard Deviation
Z17
Probability
1-2-4-6
5+8.17 +5.33 = 18.5
1.17
.43
.3336
7
4
8
6
5
6
Chapter 17 Project Management
1725
18.
Event Probability Cost ($000) Exp. Cost
1 .25 15 3.75
2 .35 25 8.75
3 .20 55 11.00
80
60
5
3 6
19.
200
160
3
2
Chapter 17 Project Management
1726
Case: The Mexican Crazy Quilt
The case combines behavioral considerations in project management with development of a foreign
subsidiary. Although some students will have minor problems getting all the names straight, I think you
will find that the case produces good discussion as well as a realistic view of the sorts of difficulties often
encountered on projects.
1. Very definitely. This was a one-time, unique effort requiring the planning and coordination of
2. Naturally, the division managers would be opposed to releasing their best people to work on the
project. In fact, while the project might be important to top management, the division managers
3. Many people are quite content to work in a stable environment, where there is little chance of
unexpected events that might upset the established routine. These people are risk-adverse; they
4. Conway realized that he might “go to the well” once too often: not every argument would be
decided in his favor. Moreover, he undoubtedly recognized that these arguments stirred up a
5. To begin with, firms must recognize the potential problems, and then set up a mechanism to deal
with them before they are full-blossomed. One possible approach to the problem might be to
Chapter 17 Project Management
1727
Case: Time, Please
Critical path is the longest path, therefore expected completion time of the project is 14 weeks.
Justification:
Path A has a higher standard deviation then path B. If we base the project completion time on path A,
then the estimated completion time (due date) of 16.58* weeks will not result in a 95% chance of
.45
0 1.645
14 17.29 Time (weeks)
Z