Chapter 16 – Scheduling
16–21
Determine job times from the schedule table, and then use Johnson’s Rule to sequence the
jobs. The job times are:
Using Johnson’s Rule, we obtain:
B
9
13
16
19
C
13
18
19
21
F
18
20
21
22
Chapter 16 – Scheduling
16–22
c. Johnson’s Rule
The Grinding flow time is 107 hours and Deburring flow time is 140 hours. The Total time is 35
hours.
d. The tradeoff is between shorter flow time in the Grinding and Deburring departments and shorter
A
3
6
10
16
6
14
16
23
E
Chapter 16 – Scheduling
16–23
Critical Ratio
Critical Ratio Calculation
Job A has the lowest critical ratio, therefore it is scheduled first and completed after 4.5 days. The
revised critical ratios are:
Critical Ratio Calculation
Job C has the lowest critical ratio, therefore it is scheduled next and it is completed after 9.7 days
(4.5 + 5.2). After the completion of Job C, the revised critical ratios are:
Critical Ratio Calculation
A
4.5
10
(10 – 0) / 4.5 = 2.22
Chapter 16 – Scheduling
16–24
Job B has the lowest critical ratio, therefore it is scheduled next and it is completed after 15.7
days (9.7 + 6). After the completion of Job B, the revised critical ratios are:
Critical Ratio Calculation
Job E has the lowest critical ratio, therefore it is scheduled next and it is completed after 18.5
days (15.7 + 2.8). After the completion of Job E, the revised critical ratios are:
Critical Ratio Calculation
Job F has the lowest critical ratio therefore it is scheduled next and it is completed after 21.8 days
(18.5 + 3.3). The final critical ratio sequence is A–C–B–E–F–D. Total completion of all six jobs
(makespan) is 23.4 days.
C
–
–
–
D
E
Chapter 16 – Scheduling
16–25
b. There are several ways to show this. One is to calculate the ratio of average flow time to average
number of jobs for each rule and then observe that they are equal. Here the ratios are
approximately 3.90. [Slight differences in ratios may arise due to rounding.]
Remaining
processing
time
Remaining
number of
operations
Slack
Remaining
number of
operations
EDD
0.55 days.
93.6/6 =
15.60 days
93.6/23.4 =
4.00
.55 days
93.6/6 =
15.60 days
93.6/23.4 =
4.00
Chapter 16 – Scheduling
16–26
Critical Ratio
Critical Ratio Calculation
e
2.5
4.5
4
0.5
Chapter 16 – Scheduling
16–27
Job E has the lowest critical ratio, therefore it is scheduled first and completed after 2.5 hours.
The revised critical ratios are:
Critical Ratio Calculation
Job A is scheduled next because Job A has the lowest critical ratio. Job A will be completed after
6 hours (2.5 + 3.5). After the completion of Job A, the revised critical ratios are:
Critical Ratio Calculation
Since Job B has the lowest critical ratio, it is scheduled next and it is completed after 8 hours (6
+ 2). After the completion of Job B, the revised critical ratios are:
Critical Ratio Calculation
B
2.0
Chapter 16 – Scheduling
16–28
Since Job F has the lowest critical ratio, it is scheduled next and it will be completed after 14
hours (8 + 6). After the completion of Job F, the revised critical ratios are:
Critical Ratio Calculation
Since Job C has the lowest critical ratio, it is scheduled next. Job C will be completed after 18.5
hours 08.12
6
5.72
time flow Average
==
C
E
–
–
–
–
–
–
Chapter 16 – Scheduling
16–29
b. Average job tardiness = 76/5 = 15.2 minutes
c. Average number of jobs in the system = 828/250 = 3.31
C
10 x
3 =
30
4 x
1 =
4
Chapter 16 – Scheduling
22. Each period’s backlog is equal to actual input – actual output. That amount is added to (or
subtracted from) the previous backlog to obtain the current (shown) backlog for the period.
Chapter 16 – Scheduling
16–31
23. Period
24. Day Mon Tue Wed Thu Fri Sat
Staff needed 2 3 1 2 4 3
Worker 1 2 3 1 2 4 3
25. Day Mon Tue Wed Thu Fri Sat
Staff needed 3 4 2 3 4 5
Worker 1 3 4 2 3 4 5
Worker 2 2 3 2 3 3 4 (tie)
1
2
3
4
5
6
Output
Planned
200
200
180
190
190
200
Actual
205
194
177
195
193
200
Deviation
-3
+5
+3
0
Cum. Dev.
+1
+4
+4
Backlog