Management Chapter 12 Homework The case asks whether the effort can be carried out with the current staff

subject Type Homework Help
subject Pages 9
subject Words 1990
subject Authors Barry Render, Jr. Ralph M. Stair, Michael E. Hanna

Unlock document.

This document is partially blurred.
Unlock all pages and 1 million more documents.
Get Access
page-pf1
Activity
Early
Early
Late
Late
Standard
Activity
time
Start
Finish
Start
Finish
Slack
Deviation
A
30
0
30
0
30
0
3.33333
B
60
30
90
60
120
30
10
C
65
30
95
30
95
0
8.333333
D
55
95
150
95
150
0
11.66667
E
30
90
120
120
150
30
1.666667
The project is expected to take 260 weeks. The critical path consists of activities A-C-D-G-H-I-
L.
2. To find the probabilities, we add the variances of the critical activities and find a project vari-
ance of 319.444. The standard deviation is 17.873. Letting X = project completion time,
3. To get a completion time of 250 days, we crash activity A for 10 days at a cost of $15,000.
This reduces the time to 250 days.
page-pf2
SOLUTION TO FAMILY PLANNING RESEARCH CENTER OF NIGERIA
CASE
This case covers three aspects of project management:
1. Critical path scheduling
2. Crashing
3. Personnel smoothing
The statement by Mr. Odaga that the project will take 94 days is a red herring. That is the sum of
all the task times that would be the length of the project only if all of the tasks were done serially
with none in parallel. Therefore, the assignment questions would be as follows:
Table 1
Latest and earliest starting times and slack
Activity
LS
ES
Slack
A. Identify faculty
8
0
8
B. Arrange transport
12
0
12
C. Identify material
0
0
0
D. Arrange accom-
modations
19
5
14
page-pf3
Figure 1 Network for Family Planning Research
Figure 2 Staffing Network for Family Planning Research
page-pf4
Table 2
Blank Staffing Chart
DAY
Activity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
A
B
Table 3
Chart Showing Each Day’s Manpower Requirements if All Activities Are Started at ES
DAY
Activity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
A
2
2
2
2
2
B
3
3
3
3
3
3
3
Table 4
page-pf5
Minimum Number of Personnel Needed for 22-Day Completion Time
DAY
Activity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
A
2
2
2
2
2
B
3
3
3
3
3
3
3
page-pf6
Table 5
Crashing Procedure
Step
Length (Days)
Total Cost
1. Original network
67
$25,400
2. Crash C 53
65
25,500
3. Crash I 72
60
25,900
4. Crash H 109
59
26,100
Second critical path emerg-
es
Crashing the schedule. Since the objective is a 60-rather than a 67-day schedule, the team
must investigate the possibilities of crashing activities on the critical path(s) to reduce project
duration using the data exhibited in the case. Table 5 shows the sequence of crashing to get to
various project lengths. Getting to 60 days is relatively easy and relatively cheap. Activity C is
reduced by 2 days at a cost of $50 per day. The next cheapest alternative is activity I, which can
SOLUTION TO INTERNET CASE
Solution to Cranston Construction Company Case
This case was based on a real construction project. The activities list for the Humanities
Building at the University of Northern Mississippi is shown in Table 1 that follows. The network
graph is shown in Figure 1. The project involved very high costs and was directly amenable to
critical path methods. The project extended over a period of approximately one year. In a project
of this length, weekly reports by the contractor would be necessary for controlling the project.
page-pf7
Table 1. Cranston Construction Times
Activity
Activity
time
Early
Start
Early
Finish
Late
Start
Late
Finish
Slack
A
28
0
28
0
28
0
B
21
0
21
7
28
7
M
23
191
214
191
214
0
N
37
214
251
214
251
0
O
14
251
265
258
272
7
P
21
251
272
251
272
0
Q
21
251
272
251
272
0
BB
35
105
140
328
363
223
CC
14
140
154
363
377
223
DD
14
105
119
188
202
83
EE
35
119
154
202
237
83
FF
21
105
126
356
377
251
page-pf8
Figure 1 Network Graph for Cranston Case
SOLUTION TO ALPHA BETA GAMMA RECORD CASE
1. The PERT diagram is shown. The activity times are the averages calculated from the formula
t = (a + 4m + b)/6
Table 1
Mean and Variance for Variable Length Activities
Activity
Mean
Variance
A
2
0.1111
B
2
0.4444
C
1
0.0278
page-pf9
PERT Networks: Thrift Print and Kwik Print showing expected values
A. Thrift Print
Total Completion time = 31.5 days
B. Kwik Print
Total Completion time = 31 days
2. The critical path has an expected length of 31.5 with variance of 0.6944. This yields a stand-
ard normal variable
3. The second solution critical path has an expected length of 31.0 with variance 0.6944. This
yields a standard normal value of 4.8; virtually all of the issues will be on time.
4. This question is behavioral in nature and can be answered in a multitude of ways. Factors in
page-pfa
SOLUTION TO HAYGOOD BROTHERS CONSTRUCTION COMPANY CASE
Using the formulas to calculate the expected times and variances for the activities yields the re-
sults in the following table.
Activity
a
m
b
t
Variance
A
4
5
6
5
0.11
B
2
5
8
5
1
H
3
4
7
4.33
0.44
I
5
7
9
7
0.44
J
10
11
12
11
0.11
The earliest, latest and slack times are shown here.
Activity
t
ES
EF
LS
LF
Slack
A
5
0
5
0
5
0
B
5
5
10
5
10
0
C
7
10
17
10
17
0
D
5
10
15
23
28
13
E
4
17
21
17
21
0
H
4.33
21
25.33
34.67
39
13.67
I
7
21
28
21
28
0
N
5.67
47
52.67
52.33
58
5.33
O
6
52
58
52
58
0
P
3
58
61
58
61
0
page-pfb
The critical path is ABCEIJLMOP (61 days). This path has a variance of 3.667 and a
standard deviation of 1.92.
Solution to Shale Oil Company Internet Case Study
1. Determine the expected shutdown time, and the probability the shutdown will be completed
one week earlier.
2. What are the probabilities that Shale finishes the maintenance project one day, two days, three
days, four days, five days, or six days earlier?
From the precedence data supplied in the problem, we can develop the following network:
page-pfc
The following table indicates the expected times, variances, and slacks needed to complete the rest of the problem.
Task
Most
Optimistic
likely
Pessimistic
E(t)
ES
EF
LS
LF
Slack
1
1
2
2.5
1.92
0.25
0
1.92
0
1.92
0
2
1.5
2
2.5
2
.17
1.92
3.92
1.92
3.92
0
11
2
2.5
3
2.5
.17
6.08
8.58
19.92
22.42
13.83
12
15
20
30
20.83
2.5
6.08
26.92
12.42
33.25
6.33
13
1
1.5
2
1.5
.17
6.42
7.92
15.92
17.42
10
14
3
5
8
5.17
.83
6.42
11.58
28.08
33.25
21.67
15
3
8
15
8.33
2
7.75
16.08
33.42
41.75
25.67
16
14
21
28
21
2.33
8.92
29.92
8.92
29.92
0
17
1
5
10
5.17
1.5
7.42
12.58
28.17
33.33
20.75
18
2
5
10
5.33
1.33
7.42
12.75
26
31.33
18.58
page-pfd
From the table, we can see that the expected shutdown time is 45.75 or 46 days. There are 9 ac-
tivities on the critical path.
Activities on the critical path
Task
2
1
0.25
0.0625
2
0.17
0.0289
3
0.33
0.1089
Therefore,
= 2.834.
As an approximation, we can use the customary equation for the Normal Distribution:
(Note: This might be a good time to discuss the difference between a continuous and a discrete
probability distribution, and the appropriate procedure for using a continuous distribution as an
approximation to a discrete, if you have not already done so.)
Finish Time
Z
Probability
One day early
0.353
36.3%
Two days early
0.706
24.0
page-pfe
3. Shale Oil is considering increasing the budget to shorten the shutdown. How do you suggest
the company proceed?
In order to shorten the shutdown, Shale Oil would have to determine the costs of decreasing
SOLUTION TO BAY COMMUNITY HOSPITAL INTERNET CASE
STUDY
1. The earliest and latest times are shown in the table below. The minimum time to complete the
project base on the original numbers is 10. The critical path is E-F.
Activity
Activity time
Early Start
Early Finish
Late Start
Late Finish
Slack
A
2
0
2
3
5
3
B
4
0
4
1
5
1
2. If activity E on the critical path is reduced by one week using express truck, the completion
time becomes 9 weeks with two critical paths: E, F and B, C, F. The completion time can be re-
duced to 8 weeks by resorting to air shipment in activity e and using overtime in activity C.
3. The cost of air shipment ($750) and overtime ($600) would increase the cost by $1,350.

Trusted by Thousands of
Students

Here are what students say about us.

Copyright ©2022 All rights reserved. | CoursePaper is not sponsored or endorsed by any college or university.