Table 5
Crashing Procedure
Second critical path emerg-
es
Crashing the schedule. Since the objective is a 60-rather than a 67-day schedule, the team
must investigate the possibilities of crashing activities on the critical path(s) to reduce project
duration using the data exhibited in the case. Table 5 shows the sequence of crashing to get to
various project lengths. Getting to 60 days is relatively easy and relatively cheap. Activity C is
reduced by 2 days at a cost of $50 per day. The next cheapest alternative is activity I, which can
SOLUTION TO INTERNET CASE
Solution to Cranston Construction Company Case
This case was based on a real construction project. The activities list for the Humanities
Building at the University of Northern Mississippi is shown in Table 1 that follows. The network
graph is shown in Figure 1. The project involved very high costs and was directly amenable to
critical path methods. The project extended over a period of approximately one year. In a project
of this length, weekly reports by the contractor would be necessary for controlling the project.