SOLUTIONS TO DISCUSSION QUESTIONS AND PROBLEMS
12-1. PERT and CPM can answer a number of questions about a project or the activities within
a project. These techniques can determine the earliest start, earliest finish, latest start, and the
12-2. There are several major differences between PERT and CPM. With PERT, three estimates
of activity time and completion are made. These are the optimistic, most likely, and pessimistic
12-3. An activity is a task that requires a fixed amount of time and resources to complete. An
12-4. Expected activity times and variances can be computed by making the assumption that ac-
tivity times follow a beta distribution. Three time estimates are used to determine the expected
activity time and variance for each activity.
12-5. The critical path consists of those activities that will cause a delay in the entire project if
they themselves are delayed. These critical path activities have zero slack. If they are delayed,
12-6. The earliest activity start time is the earliest time that an activity can be started while all
predecessor activities are completely finished. The earliest activity start times are determined
12-7. Slack is the amount of time that an activity can be delayed without delaying the entire pro-
ject. If the slack is zero, the activity cannot be delayed at all without delaying the entire project.
For any activity, slack can be determined by subtracting the earliest start from the latest start
time, or by subtracting the earliest finish from the latest finish time.
12-8. We can determine the probability that a project will be completed by a certain date by
knowing the expected project completion time and variance. The expected project completion
12-9. PERT/Cost is used to monitor and control project cost in addition to the time it takes to