Northcutt puts together foot pedal assemblies using components they buy from outside
suppliers. Below is the bill of material (BOM) for the foot pedal assembly.
Some foot pedal assemblies are used in production, many are sold to other manufacturers,
and the rest are sold as replacements.
Problem 1 Complete the master production schedule for foot pedal assemblies, shown below.
On-hand inventory at end of December = 346 Foot pedal assemblies
Month / ******** January ********** ******** February **********
Week 1 2 3 4 5 6 7 8
Forecast Demand 3,460 3,460 3,460 3,460 3,806 3,806 4,152 4,152
Problem 2 Look at your answer to Problem 1.
Suppose a customer calls up & asks to place a new order for 2,700 assemblies
in Week 1. How many of these foot pedal assemblies can Northcutt promise?