The expected project completion time is 44 weeks, and the variance is 2.167.
As can be seen in the table, the critical path for this particular problem includes activities 1,
3, 9, 11, 12, 13, 14, 17, and 18. The solution, however, is not complete. Software Development
Specialist (SDS) is not sure about the time estimates for activity 5. As indicated in the problem,
ity. We are able to go back to the original data, modify the time estimates for these activities, and
resolve the problem. Doing this will result in an expected project completion time of 47.83
weeks. The variance of the project is approximately 1.92 weeks. Will this change the critical
path? The answer is yes. The critical path now includes activities 1, 5, 11, 12, 13, 14, 17, and 18.
Activity 5 now lies along the critical path. The earliest start, earliest finish, latest start, latest fin-
ish, and slack times for all activities with the new time estimate for activity 5 of 13.83 is shown
in the table: