65
23456789
45 50 55 60 65 70 75 80
On-hand inventory at end of week 1
Week
Forecasted demand
Master production schedule
Available to promise
Booked orders
Projected ending inventory
65
23456789
45 50 55 60 65 70 75 80
On-hand inventory at end of week 1
Week
Forecasted demand
Projected ending inventory
Master production schedule
Available to promise
Booked orders
100
23456789
250 250 300 300 350 350 250 250
On-hand inventory at end of week 1
Week
Forecasted demand
Projected ending inventory
Master production schedule
Available to promise
Booked orders
100
23456789
250 250 300 300 350 350 250 250
On-hand inventory at end of week 1
Week
Forecasted demand
Projected ending inventory
Master production schedule
Available to promise
Booked orders
a.)
40
Month
19 20 21 22 23 24 25 26
200 200 200 225 225 225 200 200
On-hand inventory at end of April:
Week
Forecasted demand
************May***********
************June************
Booked orders
Projected ending inventory
Master production schedule
Available to promise
***A2*** Week: 1 2 3 4 5 6
200 200 200 300 300 300
LT (weeks): 2 200
Gross requirements
Scheduled receipts
Planned receipts
Planned orders
Projected ending inventory:
Net requirements
***A2*** Week: 1 2 3 4 5 6
200 200 200 300 300 300
LT (weeks): 3 200
Gross requirements
Scheduled receipts
Planned receipts
Planned orders
Projected ending inventory:
Net requirements
***B3*** Week: 1 2 3 4 5 6
400 400 400 400
Gross requirements
Planned receipts
Planned orders
Scheduled receipts
Projected ending inventory:
Net requirements
***B3*** Week: 1 2 3 4 5 6
400 400 400 400
LT (weeks): 1
00 0 0 0 0 0
Gross requirements
Scheduled receipts
Projected ending inventory:
Planned receipts
Planned orders
Net requirements
MPS due date
Planned receipts
Planned orders
Projected ending inventory:
Net requirements
Projected ending inventory:
Net requirements
Planned receipts
Planned orders
Scheduled receipts
Week: 1 2 3 4 5 6
LT (weeks): 0 0250 300 300 300 200
Item B Week: 1 2 3 4 5 6
# Required: 1 0250 300 300 300 200
LT (weeks): 1
Item C Week: 1 2 3 4 5 6
# Required: 2 0500 600 600 600 400
LT (weeks): 3 500 600
0 0 0 0 0 0
Item F Week: 1 2 3 4 5 6
# Required: 3 1450 1500 1300 300 200 0
Start assembly
Acme PolyBob
Gross requirements
Scheduled receipts
Gross requirements
Scheduled receipts
Planned orders
Gross requirements
Projected ending inventory:
Gross requirements
Scheduled receipts
Projected ending inventory:
Net requirements
Net requirements
Planned receipts
Planned orders
Planned receipts
Scheduled receipts
Projected ending inventory:
MPS due date
Start assembly
Gross requirements
01000 0500 0 0
Min. order: 2500 02500 02500 0 0
2500 02500 0 0 0
Week: 1 2 3 4 5 6
# Required: 2 04000 04000 04000
Min. order: 15000 0 0 0 0 0 0
0 0 0 0 0 0
Planned orders
Planned receipts
Gross requirements
Wheels
Net requirements
Planned receipts
Planned orders
Scheduled receipts
Projected ending inventory:
Net requirements
Gross requirements
Planned receipts
Planned orders
Scheduled receipts
Projected ending inventory:
Net requirements
Gross requirements
Scheduled receipts
Projected ending inventory:
Net requirements
Planned receipts
Planned receipts
Planned orders
Net requirements
Week: 1 2 3 4 5 6
2500 3000 3000 3000 2000
LT (weeks): 0 02500 3000 3000 3000 2000
05000 00001000
Week: 1 2 3 4 5 6
Triam Deluxe Computer System
MPS due date
Start assembly
Projected ending inventory:
CD-ROM drives
Scheduled receipts
Projected ending inventory:
Net requirements
Planned orders
Planned receipts
Gross requirements
Gross requirements
Scheduled receipts
a.)
916
Month
12345678
1000 1000 1250 1250 1500 1500 1750 1750
1095 950 1100 963 1125 1095 1243 1208
c.)
Booked orders
On-hand at end of December:
************January************
************February************
Week
Forecasted demand
Projected ending inventory
Master production schedule
Available to promise
Gross requirements
Scheduled receipts
Projected ending inventory:
Planned receipts
Net requirements
Compound B
Planned orders
Compound A
Planned orders
MPS mg due
MPS doses due
Compound C
Planned orders
Planned receipts
Gross requirements
Scheduled receipts
Projected ending inventory:
Net requirements
LT (weeks): 1 0 0 17000 0 0 14000 0
Week: 1 2 3 4 5 6 7
# Required: 0.5 0 0 8500 0 0 7000 0
LT (weeks): 1
1500 1500 1500 13000 13000 13000 6000 6000
Week: 1 2 3 4 5 6 7
# Required: 0.25 0 0 4250 0 0 3500 0
LT (weeks): 1 200
0200 200 00000
0 0 4050 0 0 3500 0
# Required: 0.25 010000 00000
LT (weeks): 1
00000000
010000 00000
Min. order: 4000 010000 00000
Start mixing
Gross requirements
Gross requirements
Projected ending inventory:
Gross requirements
Scheduled receipts
Projected ending inventory:
Net requirements
Planned receipts
Compound Z
Scheduled receipts
Scheduled receipts
Projected ending inventory:
Net requirements
Compound X
Planned receipts
Net requirements
Planned receipts
Planned orders
Gross requirements
Scheduled receipts
Projected ending inventory:
Net requirements
Compound Y
Planned orders
Planned orders
Projected ending inventory:
Net requirements
Planned receipts
LT (weeks): 1
Scheduled receipts
Gross requirements
PAINTING ASSEMBLY PACKING
A1.5 20.5 415 3.75
First come – first served
START END START END START END
B1.5 5.5 5.5 8.5 8.5 9.5 0
D8.5 14.5 14.5 18.5 18.5 19.5 0
Earliest due date
START END START END START END
C0 3 3 5 5 5.5 0
Critical ratio
START END START END START END
CRITICAL
RATIO
JOB
Estimated Days
TOTAL
TASK TIME
DAYS UNTIL
DUE
PACKING
DAYS LATE
JOB
PAINTING
ASSEMBLY
PACKING
DAYS LATE
JOB
PAINTING
ASSEMBLY
DAYS LATE
JOB
PAINTING
ASSEMBLY
PACKING
STEP 1 STEP 2 STEP 3
Critical ratio
START END START END START END
D Smith 0 6 6 10 10 11 0
DAYS LATE
JOB
STEP 1
STEP 2
NAME
STEP 3
CRITICAL
RATIO
NAME
JOB
Estimated Days
TOTAL
TASK TIME
DAYS UNTIL
DUE
Minneapolis Distribution Center
Month:
Week: 45 46 47 48 49 50 51 52 1 2 3 4
80 80 80 80 90 90 100 100 120 120 140 140
LT (weeks): 2
Buffalo Distribution Center
Month:
Planned receipts
Planned orders
Projected ending inventory:
Net requirements
Week: 45 46 47 48 49 50 51 52 1 2 3 4
60 60 70 70 80 80 80 80 90 90 95 95
LT (weeks): 1 100
Master Schedule
Month:
Week: 45 46 47 48 49 50 51 52
Gross requirements
Scheduled receipts
November
December
January
November
December
January
November
December
Gross requirements
Scheduled receipts
Planned receipts
Projected ending inventory:
Net requirements
Question 1.)
Week: 1 2 3 4 5 6 7 8
Question 2.)
Question 3.)
Question 4.)
Week: 1 2 3 4 5 6 7 8
Total planned orders 20000 20000 20000 20000 20000 20000 20000 20000
Refusing a customer order up-front when you know that you can not deliver is a responsible and honest
demand.
Jack’s approach to order promising has been serving as a “rule-of-thumb” in the absence of any real
information. The advantages are that even without data, he has been able to give customers a fairly