© 2020 Pearson Education, Inc., Hoboken, NJ. All rights reserved. This material is protected under all copyright laws as they currently exist.
No portion of this material may be reproduced, in any form or by any means, without permission in writing from the publisher.
14-6. Q: Tasks X, Y, and Z must be completed in series to complete a project. The three time
estimates (a, m, and b) for each task in days are: X: 30, 45, and 66 days; Y: 24, 42, and 60
days; and Z: 26, 50, and 68 days. For each task calculate (a) the expected time Te and (b) the
standard deviation 0. What is the (c) expected time Te and (d) the standard deviation 0T for
the complete project?
A: Calculation is as follows:
14-7. Q: If a project has an expected time of completion Te of 45 weeks with a standard deviation
of 7 weeks, what is the probability of completing it within one year (52 weeks)? Within 38
weeks?
A: The probability of completing the project in within Te weeks is exactly 50%. The
14-8. Q: Tasks A, B, and C must be completed in series to complete a project. The three time
estimates (a, m, and b) for each task in weeks are: A: 8, 11, and 14 weeks; B: 7, 10, and 19
weeks; and C: 10, 19, and 22 weeks. For each task calculate (a) the expected time Te and (b)
the standard deviation . What is the (c) expected time Te and (d) the standard deviation a T
for the complete project? What is the probability of completing the project (e) in 40 weeks?
(f) In 46 weeks?