1 2 3 4 5 6 Scenario x NPV
1 2 3 4 5 6 Scenario x PV
$0 $0 -$10 $0 $0 $0 -$8.40 -$2.52
40% $0 $0 $0 $0 $0 $0 $0.00 $0.00
Here the project has a positive expected NPV, so by this criterion it can be accepted.
d. Now suppose the original (no abandonment and no additional growth) project could be delayed a year.
All the cash flows would remain unchanged, but information obtained during that year would tell the
company exactly which set of demand conditions existed. Use decision tree analysis to estimate the value of
the project if it is delayed by 1 year. Hint: Discount the $10 million cost at the risk-free rate since it is known
with certainty. Show two time lines, one for operating cash flows and one for the cost, then sum their NPVs.
Future Operating Cash Flows (Discount at WACC)
Future Cost of Implementing Additional Project (Discount at Risk-free rate)
When abandonment is factored in, the very large negative NPV under bad conditions is reduced, and the
expected NPV becomes positive. Note that even though the NPV of medium is still negative, it is higher than
it would be if the project was abandoned at year 1 if conditions are medium.
c. Now assume that the project cannot be shut down. However, expertise gained by taking it on will lead to
an opportunity at the end of Year 3 to undertake a venture that would have the same cost as the original
project, and the new project’s cash flows would follow whichever branch resulted for the original project. In
other words, there would be a second $10 million cost at the end of Year 3, and then cash flows of either $9
million, $4 million, or -$1million for the following 3 years. Use decision tree analysis to estimate the value of
the project, including the opportunity to implement the new project in Year 3. Assume the $10 million cost at
Year 3 is known with certainty and should be discounted at the risk-free rate of 6 percent. Hint: do one
decision tree for the operating cash flows and one for the cost of the project, then sum their NPVs.
30%
30%