Solution 11/26/2018
Chapter: 11 Cash Flow Estimation and Risk Analysis Note: when creating student version, be sure to delete Scenario Summary worksheet. Also delete the Best and Worse case scenarios from the Scenario Manager. Also delete this message in the student version.
Problem: 18
Input Data (in thousands of dollars)
Scenario name Base Case Note: the items in red will be used in a scenario analysis.
Probability of scenario 50%
Net operating working capital/Sales 10% Key Results:
First year sales (in units) 1,000 NPV = $3,820
Sales price per unit $24.00 IRR = 22.2%
Variable cost per unit (excl. depr.) $18.00 Payback = 2.83
Nonvariable costs (excl. depr.) $1,000
Inflation in prices and costs 3.0%
Estimated salvage value at year 4 $500
Depreciation years Year 1 Year 2 Year 3 Year 4
Depreciation rates 20.00% 32.00% 19.20% 11.52%
WACC for average-risk projects 10%
Intermediate Calculations
Units sold 1,000 1,000 1,000 1,000
Sales price per unit (excl. depr.) $24.00 $24.72 $25.46 $26.23
Variable costs per unit (excl. depr.) $18.00 $18.54 $19.10 $19.67
Nonvariable costs (excl. depr.) 1,000 1,030 1,061 1,093
Sales revenue $24,000 $24,720 $25,462 $26,225
Required level of net operating working capital $2,400 $2,472 $2,546 $2,623 $0
Basis for depreciation $10,000
Annual equipment depr. rate 20.00% 32.00% 19.20% 11.52%
Annual depreciation expense $2,000 $3,200 $1,920 $1,152
Salvage value $500
Profit (or loss) on salvage -$1,228
Tax on profit (or loss) -$307
Net cash flow due to salvage $807
Sales revenue $24,000 $24,720 $25,462 $26,225
Variable costs 18,000 18,540 19,096 19,669
Nonvariable operating costs 1,000 1,030 1,061 1,093
Depreciation (equipment) 2,000 3,200 1,920 1,152
Oper. income before taxes (EBIT) $3,000 $1,950 $3,385 $4,312
Taxes on operating income (40%) 750 488 846 1,078
Net operating profit after taxes $2,250 $1,463 $2,538 $3,234
Add back depreciation 2,000 3,200 1,920 1,152
Equipment purchases -$10,000
Cash flow due to change in NOWC -$2,400 -$72 -$74 -$76 $2,623
Net cash flow due to salvage $807
Net Cash Flow (Time line of cash flows) -$12,400 $4,178 $4,588 $4,382 $7,815
Key Results: Appraisal of the Proposed Project
Net Present Value (at 10%) = $3,820
Discounted Payback = 3.19
Data for Payback Years
0 1 2 3 4
Data for Discounted Payback Years
0 1 2 3 4
Years
Years
-20% 800 $1,006
-10% 900 $2,413
0% 1,000 $3,820
a. Develop a spreadsheet model, and use it to find the project’s NPV, IRR, and payback.
Webmasters.com has developed a powerful new server that would be used for corporations’ Internet activities. It
would cost $10 million at Year 0 to buy the equipment necessary to manufacture the server. The project would
require net working capital at the beginning of each year in an amount equal to 10% of the year’s projected sales;
for example, NWC0 = 10%(Sales1).
Webmasters’ federal-plus-state tax rate is 25%. Its cost of capital is 10% for average-risk projects, defined as
projects with a coefficient of variation of NPV between 0.8 and 1.2. Low-risk projects are evaluated with a WACC of
8%, and high-risk projects at 13%. Also, the project’s returns are expected to be highly correlated with returns on
believes that variable costs would amount to $18,000 per unit. After Year 1, the sales price and variable costs will
increase at the 3% inflation rate.
should be the number 1,000 and NOT have the formula =D31 in
that cell. This is because you’ll use D31 as the column input
cell in the data table and if Excel tries to iteratively replace Cell
D31 with the formula =D31 rather than a series of numbers,
Excel will calculate the wrong answer. Unfortunately, Excel
won’t tell you that there is a problem, so you’ll just get the
wrong values for the data table!