Economics Chapter 26 Homework What The Expected NPV Answer Initial Cost

subject Type Homework Help
subject Pages 19
subject Words 3977
subject Authors Eugene F. Brigham, Michael C. Ehrhardt

Unlock document.

This document is partially blurred.
Unlock all pages and 1 million more documents.
Get Access
page-pf1
Answers and Solutions: 26 - 1
Chapter 26
Real Options
ANSWERS TO END-OF-CHAPTER QUESTIONS
26-1 a. Real options occur when managers can influence the size and risk of a project’s cash
flows by taking different actions during the project’s life. They are referred to as real
options because they deal with real as opposed to financial assets. They are also
called managerial options because they give opportunities to managers to respond to
changing market conditions. Sometimes they are called strategic options because
they often deal with strategic issues. Finally, they are also called embedded options
because they are a part of another project.
c. Decision trees are a form of scenario analysis in which different actions are taken in
different scenarios.
26-2 Postponing the project means that cash flows come later rather than sooner; however,
waiting may allow you to take advantage of changing conditions. It might make sense,
however, to proceed today if there are important advantages to being the first competitor
to enter a market.
page-pf2
Answers and Solutions: 26 - 2
SOLUTIONS TO END-OF-CHAPTER PROBLEMS
26-1 a. 0 1 2 20
├─────┼─────┼────── ────┤
-20 3 3 3
NPV = $1.074 million.
b. Wait 1 year:
Note though, that if the tax is imposed, the NPV of the project is negative and therefore
would not be undertaken. The value of this option of waiting one year is evaluated as
0.5($0) + (0.5)($ 5.920) = $2.96 million.
Since the NPV of waiting one year is greater than going ahead and proceeding with the
project today, it makes sense to wait.
page-pf3
Answers and Solutions: 26 - 3
26-2 a. 0 1 2 3 4
├─────┼─────┼─────┼─────┤
-8 4 4 4 4
NPV = $4.6795 million.
b. Wait 2 years:
10%
page-pf4
Answers and Solutions: 26 - 4
26-3 a. 0 1 2 20
├─────┼─────┼────── ────┤
-300 40 40 40
NPV = -$19.0099 million. Don’t purchase.
b. Wait 1 year:
NPV @
0 1 2 3 4 21 Yr. 0
| | | | | |
50% Prob. 0 -300 30 30 + 280 0 0 -$27.1468
| | | | | |
50% Prob. 0 -300 50 50 50 50 45.3430
13%
r = 13%
page-pf5
Answers and Solutions: 26 - 5
26-4 a. 0 1 14 15
| | | |
-6,200,000 600,000 600,000 600,000
c. If they proceed with the project today, the project’s expected NPV = (0.5 -
$2,113,481.31) + (0.5 $1,973,037.39) = $70,221.96. So, Hart Enterprises would not
do it.
d. Since the project’s NPV with the tax is negative, if the tax were imposed the firm
would abandon the project. Thus, the decision tree looks like this:
12%
page-pf6
Answers and Solutions: 26 - 6
e. NPV @
0 1 Yr. 0
50% Prob. | |
Taxes NPV = ? -1,500,000 $ 0.00
+300,000 = NPV @ t = 1
r = 12%
wouldn’t do
page-pf7
Answers and Solutions: 26 - 7
26-5
a.
b. 0 1 2 3 4
40% Prob. | | | | |
Good -20,000 25,000 25,000 25,000 25,000
-20,000 (r = 6%)
Bad | | | | |
60% Prob. -20,000 5,000 5,000 0 0
r = 10%
page-pf8
Answers and Solutions: 26 - 8
26-6 P = PV of all expected future cash flows if project is delayed. From Problem 14-1 we
know that PV @ Year 1 of Tax Imposed scenario is $15.45 and PV @ Year 1 of Tax Not
Imposed Scenario is $26.69. So the PV is:
P = [0.5(15.45)+ 0.5(26.690] / 1.13 = $18.646.
X = $20.
V = P[N(d1)] -
trRF
Xe
[N(d2)]
page-pf9
Answers and Solutions: 26 - 9
26-7 P = PV of all expected future cash flows if project is delayed. From Problem 14-1 we
know that PV @ Year 2 of Low CF Scenario is $6.974 and PV @ Year 2 of High CF
Scenario is $13.313. So the PV is:
P = [0.1(6.974)+ 0.9(13.313] / 1.102 = $10.479.
X = $9.
d2 = 1.9010 - (.0111)0.5 (2)0.5 = 1.7520
From Excel function NORMSDIST, or approximated from the table in Appendix A:
N(d1) = 0.9713
N(d2) = 0.9601
26-8 P = PV as of time zero of all expected future cash flows if the project is repeated starting
in year 2. Note it includes both the good cash flows and the bad cash flows since as of
now, we don’t know which outcome will result, and P excludes the $20,000 investment
in the franchise.
0 1 2 3 4
40% Prob. | | | | |
Good 25,000 25,000
r = 10%
page-pfa
Answers and Solutions: 26 - 10
The time to expiration is the time you decide whether or not to extend the franchise, and
is at the end of year 2.
Although the problem stated to assume the variance of the project’s rate of return was
0.2025, we’ll also calculate it using the direct method. First calculate the rates of return
using the decision tree. To do this, calculate the present values of the two branches as of
the exercise date, year 2, and the rates of return assuming the initial value of the
investment was P = $18,646.
0 1 2 3 4
The expected value of these two returns is 52.54(0.40) 31.78(0.60) = 1.95% [Note: this
isn’t 10% as you might hope! The 2-year returns are 43,388/18,646 1 = 132.69% in
the good state and 8,678/18,646 1 = -53.46% in the bad state. The expected value of
these is 132.69% (0.40) - 53.46% (0.60) = 21.0%, which is exactly 10% compounded
twice: 0.21 = (1.10)2 1.]
page-pfb
Answers and Solutions: 26 - 11
To calculate the variance of the project’s returns using the indirect method, first calculate
the standard deviation of the value at year 2. The value is either 43,388 (probability
40%) or 8,678 (probability 60%).
P = $18,646
X = $20,000
t = 2.
rRF = 0.06.
σ2 = 0.2025
d1 = ln[18.646/20] + [0.06 + .5(0.2025)](2) = 0.3966
(0.2025)0.5 (2)0.5
page-pfc
Answers and Solutions: 26 - 12
SOLUTION TO SPREADSHEET PROBLEMS
page-pfd
Mini Case: 26 - 13
MINI CASE
Assume that you have just been hired as a financial analyst by Tropical Sweets Inc., a mid-
sized California company that specializes in creating exotic candies from tropical fruits
such as mangoes, papayas, and dates. The firm's CEO, George Yamaguchi, recently
returned from an industry corporate executive conference in San Francisco, and one of the
sessions he attended was on real options. Since no one at Tropical Sweets is familiar with
the basics of real options, Yamaguchi has asked you to prepare a brief report that the
firm's executives could use to gain at least a cursory understanding of the topics.
To begin, you gathered some outside materials the subject and used these materials to
draft a list of pertinent questions that need to be answered. In fact, one possible approach
to the paper is to use a question-and-answer format. Now that the questions have been
drafted, you have to develop the answers.
a. What are some types of real options?
Answer: 1. Investment timing options
2. Growth options
a. Expansion of existing product line
b. What are five possible procedures for analyzing a real option?
Answer: 1. DCF analysis of expected cash flows, ignoring option.
page-pfe
Mini Case: 26 - 14
c. Tropical Sweets is considering a project that will cost $70 million and will
generate expected cash flows of $30 per year for three years. The cost of capital
for this type of project is 10 percent and the risk-free rate is 6 percent. After
discussions with the marketing department, you learn that there is a 30 percent
chance of high demand, with future cash flows of $45 million per year. There is
a 40 percent chance of average demand, with cash flows of $30 million per year.
If demand is low (a 30 percent chance), cash flows will be only $15 million per
year. What is the expected NPV?
Answer: Initial Cost = $70 Million
Expected Cash Flows = $30 Million Per Year For Three Years
Cost Of Capital = 10%
PV Of Expected CFs = $74.61 Million
Expected NPV = $74.61 - $70
= $4.61 Million
page-pff
Mini Case: 26 - 15
d. Now suppose this project has an investment timing option, since it can be
delayed for a year. The cost will still be $70 million at the end of the year, and
the cash flows for the scenarios will still last three years. However, Tropical
Sweets will know the level of demand, and will implement the project only if it
adds value to the company. Perform a qualitative assessment of the investment
timing option’s value.
Answer: If we immediately proceed with the project, its expected NPV is $4.61 million.
However, the project is very risky. If demand is high, NPV will be $41.91
page-pf10
Mini Case: 26 - 16
e. Use decision tree analysis to calculate the NPV of the project with the investment
timing option.
Answer: The project will be implemented only if demand is average or high.
Here is the time line:
0 1 2 3 4
f. Use a financial option pricing model to estimate the value of the investment
timing option.
Answer: The option to wait resembles a financial call option-- we get to “buy” the project for
$70 million in one year if value of project in one year is greater than $70 million.
page-pf11
Mini Case: 26 - 17
Step 1: Find the value of all cash flows beyond the exercise date discounted back to
the exercise date. Here is the time line. The exercise date is year 1, so we discount
all future cash flows back to year 1.
0 1 2 3 4
High $45 $45 $45
Average $30 $30 $30
Low $15 $15 $15
page-pf12
Mini Case: 26 - 18
Following is an explanation of each approach.
Subjective estimate:
The typical stock has σ2 of about 12%. Most projects will be somewhat riskier than
the firm, since the risk of the firm reflects the diversification that comes from having
many projects. Subjectively scale the variance of the company’s stock return up or
down to reflect the risk of the project. The company in our example has a stock with
a variance of 10%, so we might expect the project to have a variance in the range of
12% to 19%.
Expected Return = 0.3(0.65) + 0.4(0.10) + 0.3(-0.45)
= 10%.
2 = 0.3(0.65-0.10)2 + 0.4(0.10-0.10)2 + 0.3(-0.45-0.10)2
= 0.182 = 18.2%.
page-pf13
Mini Case: 26 - 19
The indirect approach:
Given a current stock price and an anticipated range of possible stock prices at some
We previously calculated the value of the project at the time the option expires, and
we can use this to calculate the expected value and the standard deviation.
Value At Expiration
Year 1
High $111.91
Average $74.61
Low $37.30
page-pf14
Mini Case: 26 - 20
Now, we proceed to use the OPM:
= $10.98.
g. Now suppose the cost of the project is $75 million and the project cannot be
delayed. But if Tropical Sweets implements the project, then Tropical Sweets
will have a growth option. It will have the opportunity to replicate the original
project at the end of its life. What is the total expected NPV of the two projects
if both are implemented?
Answer: Suppose the cost of the project is $75 million instead of $70 million, and there is no
option to wait.
NPV = PV of future cash flows - cost
page-pf15
Mini Case: 26 - 21
h. Tropical Sweets will replicate the original project only if demand is high. Using
decision tree analysis, estimate the value of the project with the growth option.
Answer: The future cash flows of the optimal decisions are shown below. The cash flow in
year 3 for the high demand scenario is the cash flow from the original project and the
cost of the replication project.
page-pf16
Mini Case: 26 - 22
i. Use a financial option model to estimate the value of the growth option.
Answer: X = Strike Price = Cost Of Implement Project = $75 million.
RRF = Risk-Free Rate = 6%.
T = Time To Maturity = 3 years.
P = Current Price Of Stock = Current Value Of The Project’s Future Cash Flows.
σ2 = Variance Of Stock Return = Variance Of Project’s Rate Of Return.
page-pf17
Direct approach for estimating σ2:
From our previous analysis, we know the current value of the project and the value
for each scenario at the time the option expires (year 3). Here is the time line:
page-pf18
Mini Case: 26 - 24
The indirect approach:
First, find the coefficient of variation for the value of the project at the time the option
expires (year 3).
We previously calculated the value of the project at the time the option expires, and
we can use this to calculate the expected value and the standard deviation.
page-pf19
Mini Case: 26 - 25
j. What happens to the value of the growth option if the variance of the project’s
return is 14.2 percent? What if it is 50 percent? How might this explain the
high valuations of many dot.com companies?
Answer: If risk, defined by σ2, goes up, then value of growth option goes up (see the file Ch26
mini case.xls for calculations):
σ2 = 4.7%, option value = $5.92

Trusted by Thousands of
Students

Here are what students say about us.

Copyright ©2022 All rights reserved. | CoursePaper is not sponsored or endorsed by any college or university.