Total Total
Committed Estimated
Non- and Non– Estimated Cost Variance
Total Committed Committed Committed Cost at Over /
Original Change Estimate Committed Costs Costs Costs To Completion (Under)
Code Description Estimate Orders (C + D) Costs Invoiced Invoiced (F + H) Complete (I + J) (K – E)
1100 Supervision 36,000 – 36,000 – – 7,985 7,985 28,000 35,985 (15)
1700 Temporary Utilities 6,700 – 6,700 – – 1,615 1,615 5,211 6,826 126
1900 Clean-up 4,600 – 4,600 – – – – 4,600 4,600 –
3300 Footing and Foundation—Labor 3,400 – 3,400 – – 3,685 3,685 – 3,685 285
3400 Footing and Foundation—Concrete 3,500 – 3,500 – – 3,321 3,321 – 3,321 (179)
3450 Concrete Pump 1,700 – 1,700 – – 1,569 1,569 – 1,569 (131)
3500 Slab/Floor—Labor 2,100 – 2,100 – – 1,896 1,896 – 1,896 (204)
3600 Slab/Floor—Concrete 6,800 – 6,800 – – 6,955 6,955 – 6,955 155
3900 Rebar 1,100 – 1,100 – – 999 999 – 999 (101)
4100 Masonry 44,000 – 44,000 42,136 36,000 – 42,136 – 42,136 (1,864)
5100 Structural Steel 11,000 – 11,000 10,250 – – 10,250 – 10,250 (750)
5300 Joist and Deck 15,500 – 15,500 15,500 – – 15,500 – 15,500 –
5900 Erection 8,600 – 8,600 8,200 – – 8,200 – 8,200 (400)
6110 Rough Carpentry 500 – 500 – – – – 500 500 –
6120 Lumber 900 – 900 875 – – 875 – 875 (25)
7200 Insulation 1,700 – 1,700 1,802 – – 1,802 – 1,802 102
7500 Roofing 9,000 – 9,000 8,875 – – 8,875 – 8,875 (125)
7700 Roof Specialties 1,000 – 1,000 945 – – 945 – 945 (55)
8110 Metal Doors and Frames 2,900 – 2,900 2,725 – – 2,725 – 2,725 (175)
8400 Store Fronts 9,500 – 9,500 9,100 – – 9,100 – 9,100 (400)
8700 Hardware 1,900 – 1,900 1,864 – – 1,864 – 1,864 (36)
9100 Drywall 6,700 – 6,700 6,898 – – 6,898 – 6,898 198
9200 Ceramic Tile 2,100 – 2,100 1,999 – – 1,999 – 1,999 (101)
9300 Acoustical Treatment 7,200 – 7,200 6,995 – – 6,995 – 6,995 (205)
9400 Carpet and Vinyl 5,500 – 5,500 5,354 – – 5,354 – 5,354 (146)
9800 Paint 8,200 – 8,200 8,000 – – 8,000 – 8,000 (200)
10400 Signage 500 – 500 486 – – 486 – 486 (14)
10800 Toilet & Bath Accessories 1,000 – 1,000 965 – – 965 – 965 (35)
12300 Cabinetry and Countertops 10,000 – 10,000 9,865 – – 9,865 – 9,865 (135)
21100 Fire Sprinklers 6,700 – 6,700 7,000 – – 7,000 – 7,000 300
22100 Plumbing 24,000 – 24,000 22,115 – – 22,115 – 22,115 (1,885)
23100 HVAC 23,000 – 23,000 23,850 – – 23,850 – 23,850 850
26100 Electrical 19,000 – 19,000 17,825 – – 17,825 – 17,825 (1,175)
31100 Grading and Excavation 6,300 – 6,300 6,150 3,150 – 6,150 – 6,150 (150)
32100 Asphalt 17,000 – 17,000 17,569 – – 17,569 – 17,569 569
32200 Site Concrete—Labor 1,000 – 1,000 – – – – 1,000 1,000 –
32300 Site Concrete—Concret e 1,000 – 1,000 – – – – 960 960 (40)
32500 Landscaping 1,000 – 1,000 – – – – 1,000 1,000 –
33100 Sanitary Sewer 1,000 – 1,000 1,359 – – 1,359 – 1,359 359
33200 Water Line 1,000 – 1,000 1,125 – – 1,125 – 1,125 125
Profit and Overhead 32,000 – 32,000 32,000 – – 32,000 – 32,000 –