10
© 2015 Cengage Learning. All rights reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
a. The court judgment seeks to: (1) put the injured party in the position it would
have been in had there been no breach, or (2) restore the injured party to the
position it occupied before performance began, or (3) prevent the breaching
party’s unjust enrichment.
3.) In regards to limits on recovery, what are the four primary factors that must be met
or proven for a claimant to receive compensation?
4.) What are the five principal claims made by contractors against owners?
5.) If a contractor had an original contract price of $800,000, had already expended
$210,000 in part performance, estimates that the cost of completion would be
$625,000 and has already received $175,000 in progress payments, how much
would that contractor be entitled to in damages if you were to use the reasonable
cost of completion formula?
6.) If the data is available, which is the best method of proving damages?
7.) Under the Eichleay formula, what three things must the claimant prove in order to
use this formula?
8.) Assuming actual data is not available, what are the two techniques that are used for
a contractor to measure productivity losses for a claim?
9.) What is the Single Recovery Rule?
10.) What is “economic waste” and what role does it play in measuring the
owner’s damages?