87
Chapter 25
Teaching Chapter 25 has its problems, principally because of the terminology
and complexity of the surety transaction. The best way we can think of to teach
the material here is to slowly and carefully go over a surety bond. Figures 25.1
and 25.2 illustrate graphically the difference between performance and payment
bonds, using both standard and Restatement terminology. We would also
suggest that the instructor look at Appendix I (on the website) which contains
A3122010.
Examine A3122010 Paragraph 3.1 of the performance bond. It conditions the
surety’s obligation upon the owner notifying the contractor and the surety that it is
considering a contractor default and has requested and attempted to arrange a
conference with the contractor and surety to be held not later than 10 days after
completion of the project or correction of defective work is not the sole limit of the
surety’s obligation. A312 also states that the surety will not be liable for
obligations of the contractor that are unrelated to the construction contract.
Section 25.15 addresses bad faith claims, taking as a starting point the
statutory regulation of insurers. However, the common law duty of good faith and
bond are purchased by the principal so as to provide protection to the obligees:
the owner in the case of a performance bond and the subcontractors in the case
of a payment bond. By contrast, licensing bonds are statutorily mandated and
their value is determined by statute, rather than by the value of the project. While
88
© 2015 Cengage Learning. All rights reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
owners who demand performance and payment bonds pay the premium, owners
do not pay additional consideration (i.e., money) for licensing bonds because, at
least in theory, only a licensed contractor may perform construction work.
Moreover, since, at least in theory, an owner cannot hire an unlicensed
contractor, there is no incremental additional licensing bond cost attributable to a
particular project. Finally, the state statute permits the deposit of cash with the
state agency (in lieu of a licensing bond). Since the homeowners admit they
would have no claim against the state agency holding a cash deposit, it makes
no sense to make the surety liable merely because the contractor chose instead
to get a licensing bond.
The O’Connor case illustrates two points. First, while surety bad faith law
arose by analogy from insurer bad faith law, the comparison between obligee
Answers to Chapter Questions
1. What are the requirements for a prime contractor under the Miller Act?
2. What is the function of a surety?
3. What is the function of a bid bond?
4. According to AIA A3122010 Section 3, what are the three steps the owner
should take in order to trigger the surety’s bond obligations?
5. What are the four courses of action the performance bond surety has the
option of using in fulfilling its bond obligations, according to the AIA A312
2010?
89
© 2015 Cengage Learning. All rights reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
a. The four courses of action are (1) arrange for the original contractor,
with the owner’s consent, to complete the contract, (2) complete the
project itself, including through use of independent contractors, (3)
obtain bids or negotiated proposals from qualified contractors
acceptable to the owner and arrange for the owner to continue work
with that new contractor, backed up by new performance and
payment bonds, and (4) waive its right to perform and complete, and
instead (i) after investigation, pay the owner its costs of completion or
(ii) deny liability in whole or in part.
6. What are some actions that an owner may take that could discharge the
surety (release the surety from its obligations under the bond)?
7. What is the purpose of a payment bond?
8. According to the AIA A3122010 document, who may sue on a payment
bond?
9. What did the federal court of appeals state was included in “sums justly due”
in a Miller Act payment bond in the case, United States for Use and Benefit of
Perlun Construction Co. v. Harvesters Group, Inc.? What was the basis for the
court’s reasoning?
10. What is a consequence to the surety if a court finds it acted in bad faith in the
(non)performance of its bond obligations?