76
that milestone dates had not been met, but not that this was a substantial
breach or sufficient ground for termination.
The court upheld the determination by the trial judge that the certificate was
defective, as it did not certify what was required under old Paragraph 14.2.2
(The trial judge pointed to the fact that the architect was unlicensed.) The
That the certificate was defective, held the court, did not deprive the board of
its common law right to claim that it had proper grounds to terminate the
contractor. It pointed to old Paragraphs 13.4.1 and 14.2.2 that state the
contractual remedies are not exclusive. The court concluded that a proper
certificate is not a condition precedent to the board’s exercise of its common
law rights. The board’s traditional burden to establish a material breach would
have been largely exempted by the issuance of a proper certificate. The court
did not have to decide how much finality to extend to a proper certificate, but it
seems clear that issuance would have been very beneficial to the board.
The case raises many questions. Would a proper certificate by an unlicensed
architect have been valid? The trial court seemed troubled by this, but the
appellate court was not. It did not have to address this issue, as it was clear
What of the architect’s refusal to give the certificate because he had no personal
knowledge? This would not accord with the intention of the parties. They knew
the architect was not on the site every day. More likely, the architect should
have conducted an investigation of the type specified in old Paragraph 4.3
dealing with claims. (Perhaps his unwillingness to do so was based upon his
unlicensed status.)
The Ingrassia court held that the school board’s failure to obtain its architect’s
certificate simply meant that the board’s right to terminate must be under the
common law. Contrast this with Town of Plainfield v. Paden Eng’g Co., 943
N.E.2d 904 (Ind.App.2011), holding that the town’s termination of the contractor
for default was wrongful where the town did not obtain an architect certification
as required by the AIA contract.