57
© 2015 Cengage Learning. All rights reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
Chapter 17
One way to approach the payment process is to postulate two hypotheticals.
The first is a home owner building a garage and the second, a large commercial
structure. Ask the students when the home owner would have to pay if there
were no provision in the contract dealing with payments and then postulate a
contractor who cannot accept this and wishes to be paid as it works. Then ask
them to structure a payment schedule which would take into account the needs
of both owner and contractor. Move then to a large project and the need for a
complex payment process.
While the exercise may be boring to many students, it is useful to introduce
this topic by reading AIA language or any other sophisticated contract dealing
with the topic. The payment process expressed in A2012007, Article 9 is
complex. Will students appreciate the importance of going though what appears
to be boring language? Yet the language in such an agreement is the culmination
of a host of problems that have come up and gives a good indication of the types
of issues that arise in construction.
Joint checks (Section 17.4) will need class explanation. While the owner
clearly benefits from the rule, does it unfairly deprive a subcontractor (who may
have little economic power over a prime contractor) of a statutory remedy in the
form of a mechanics’ lien?
Section 17.5 (payment certifications) replays the issues discussed in Section
10.3B, dealing with design professional inspection of the contractor’s work and
the concomitant duty to protect the owner. In the case of payment certifications,
liability may extend as well to a claim by the payment bond surety.
The role of the lender (Section 17.6) provides an opportunity to review the
financing of a large construction project. (A rereading of Section 7.6 is merited.)
Where the project involves a homeowner who does not employ an independent
design professional, to what extent may the owner look to the bank for
protection?
As noted in Section 17.8, increasingly statutes deal with delayed payments. In
March 1982, the Congress enacted the Prompt Payment Act (31 U.S.C.A. § 3901
et. seq.) which requires the federal government to pay its bills on time or face
interest penalties and attorneys’ fee charges.
After an enactment of that legislation a coalition of contractors and suppliers
undertook a major job to encourage state legislatures to pass similar measures.
A clear majority of the states have such laws on their books. Most of these laws
deal with public agencies and public contracts. Some, however, regulate private
agreements.
58
© 2015 Cengage Learning. All rights reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
Common law regulation of delayed payment or nonpayment reprises the
concept of a material breach, introduced in Section 3.7B. A class discussion
directing the students’ attention to Section 3.7B should help bridge the gap
between an abstract, legal concept (material breach) and a concrete,
construction dispute (owner nonpayment for one day, one week, two weeks,
etc.).
Beginning with Section 17.9, the second half of Chapter 19 deals with project
completion, including payment issues.
Section 17.10 deals with the substantial performance doctrine. The facts of
Jacob & Youngs, Inc. v. Kent case illustrates well the underlying rationale for this
doctrine. The contractor is clearly in breach of contract, but what is the proper
remedy?
The doctrine is subject to abuse: used by contractors to more or less complete
a job and then walk away from it and be able to recover under this doctrine. Ask
the students what they think of the substantial performance doctrine. Some may
believe it is absolutely essential in the construction process for reasons that have
been noted in the book. Others may insist that overuse of the substantial
performance doctrine even if it is accompanied by proper price reductions can
encourage the contractor to walk away when a job has not been completed. (A
hidden cost to the owner not recognized by the doctrine: The administrative cost
of finding a contractor willing to come in and wrap up another’s work. Not only
may the new contractor not be interested in such a small project, but it may fear
liability arising out of latent defects in the first contractor’s work.)
An instructor who wants to develop this topic should read the Tolstoy case
cited in note 21 and give the facts of that case to the students. It will be a good
illustration of how a contractor in a contract which involves an unsophisticated
consumer may seek to use the doctrine to recover when there is a host of minor
defects he refuses to fix.
As to the Plante case, ask students whether the owners should be able to
recover some amount for the misplaced wall if they can show that the living room
will no longer be able to take furniture because of it being a foot narrower than
specified. Also ask whether this case really involves, at least as far as the wall is
concerned, damages which can be considered more aesthetic than economic. If
so, how should claims be measured?
Answers to Chapter Questions
1.) How does the progress payment system work in the construction industry?
a. In the progress payment system the contractor is paid incrementally
commensurate with the percentage of work completed. The common law’s
“work first and then be paid” rule is divided into units of the work: as each
59
© 2015 Cengage Learning. All rights reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
unit is completed, payment is due for that work. The units can be either
stages of completion or time elapsed.
2.) What are the purposes for retainage?
a. One purpose of retainage is to provide money of which claims that the
owner has against the contractor can be collected without the necessity of a
lawsuit. If a project is nearly complete, but small defects remain and the
contractor fails to correct the problem, the owner may use the retainage to
effectuate these repairs, and then refund the remainder to the contractor.
Another purpose of the retainage is to provide the owner with money with
which to pay any subcontractor or supplier liens.
3.) What are two tactics that seek to protect the owner against future claims by unpaid
subcontractors or suppliers?
a. Some contracts require the contractor to give the owner assurance or proof
that the prime has paid its subcontractors and suppliers when payment
applications are made. Alternatively, contracts may require the prime
contractor to demand lien waivers from the subcontractors as a condition
for payment, in which the subcontractor gives up its right to a mechanic’s
lien for the work covered in the progress payment.
4.) What are the implications if a design professional undercertifies or overcertifies a
payment application?
a. Undercertification impairs the contractor’s cash flow, and overcertification
diminishes the retainage.
5.) If a contractor obtains a loan from a lender to finance construction, how might the
lender use an assignment to secure payback of the loan?
a. An assignment transfers the right to receive payment and effectuates a
change of ownership in the rights transferred. It is a more substantial
security than a promise. As the contractor performs and becomes entitled to
progress payments, those payments are made either directly to the lender or
by joint check to the contractor and lender.
6.) What are the differences in rules of the courts in the GEM Industrial, Inc. v. Sun Trust
Bank and White v. AAMG Construction Lender Center on one hand, and Alpine Bank v.
Hubbell on the other?
a. In GEM and White, both courts found the construction lender liable to the
owner when the lender’s inspector had discovered defective or incomplete
construction, yet still made the payments to the contractor. In Hubbell, the
court enforced a Limitation of Responsibility provision in the loan
agreement and found the lender not liable to the owner/borrower. The
owner could not rely upon the bank to protect the owner from the
contractor’s improper performance.
7.) What is the Prompt Payment Act and what are the penalties if a contractor is found
to break this act?
a. Under the federal Prompt Payment Act, a contractor must pay its
subcontractors for satisfactory performance within seven days of receiving
payment from the federal agency. Failure to pay on time subjects the
contractor to an interest penalty owed to the subcontractor. Subcontractors
have the same obligation to pay subsubcontractors.
8.) What is substantial completion and what are the ramifications to the owner and
contractor of the contractor achieving substantial completion?
a. Substantial completion is the point at which the project may be occupied
and used for its intended purpose. It may entitle the contractor to payment
60
© 2015 Cengage Learning. All rights reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
of the retainage, less adjustments for incomplete or defective work.
Warranties generally begin to run at the time of substantial completion, as
does the statute of repose. Achieving substantial completion is also a
prerequisite to the contractor’s use of statutory remedies, such as filing a
mechanic’s lien. Liquidated damages may begin to run from the date of
substantial completion or final completion, depending on the wording of the
contract.
9.) What is the substantial performance doctrine and how does it function?
a. The substantial performance doctrine provides the contractor with a means
of achieving at least partial payment notwithstanding its contract breach. In
its simplest form, it requires the owner to pay the balance of the
construction contract price if the contractor has substantially performed,
leaving the owner a claim for damages based on failure of the contractor to
perform strictly in accordance with the contract requirements.
10.) What is restitution, what is its purpose, and when might a contractor use the
doctrine in the project completion process?
a. Restitution may enable the contractor to recover for any net benefit that its
performance has conferred on the owner. One purpose of restitution is to
avoid unjust enrichment to the owner. A contractor may invoke use of
restitution if it has not performed sufficiently to achieve the benefits of the
substantial performance doctrine, yet is otherwise done working on the
project.