59
© 2015 Cengage Learning. All rights reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
unit is completed, payment is due for that work. The units can be either
stages of completion or time elapsed.
2.) What are the purposes for retainage?
a. One purpose of retainage is to provide money of which claims that the
owner has against the contractor can be collected without the necessity of a
lawsuit. If a project is nearly complete, but small defects remain and the
contractor fails to correct the problem, the owner may use the retainage to
effectuate these repairs, and then refund the remainder to the contractor.
Another purpose of the retainage is to provide the owner with money with
which to pay any subcontractor or supplier liens.
3.) What are two tactics that seek to protect the owner against future claims by unpaid
subcontractors or suppliers?
a. Some contracts require the contractor to give the owner assurance or proof
that the prime has paid its subcontractors and suppliers when payment
applications are made. Alternatively, contracts may require the prime
contractor to demand lien waivers from the subcontractors as a condition
for payment, in which the subcontractor gives up its right to a mechanic’s
lien for the work covered in the progress payment.
4.) What are the implications if a design professional undercertifies or overcertifies a
payment application?
a. Undercertification impairs the contractor’s cash flow, and overcertification
diminishes the retainage.
5.) If a contractor obtains a loan from a lender to finance construction, how might the
lender use an assignment to secure pay–back of the loan?
a. An assignment transfers the right to receive payment and effectuates a
change of ownership in the rights transferred. It is a more substantial
security than a promise. As the contractor performs and becomes entitled to
progress payments, those payments are made either directly to the lender or
by joint check to the contractor and lender.
6.) What are the differences in rules of the courts in the GEM Industrial, Inc. v. Sun Trust
Bank and White v. AAMG Construction Lender Center on one hand, and Alpine Bank v.
Hubbell on the other?
a. In GEM and White, both courts found the construction lender liable to the
owner when the lender’s inspector had discovered defective or incomplete
construction, yet still made the payments to the contractor. In Hubbell, the
court enforced a Limitation of Responsibility provision in the loan
agreement and found the lender not liable to the owner/borrower. The
owner could not rely upon the bank to protect the owner from the
contractor’s improper performance.
7.) What is the Prompt Payment Act and what are the penalties if a contractor is found
to break this act?
a. Under the federal Prompt Payment Act, a contractor must pay its
subcontractors for satisfactory performance within seven days of receiving
payment from the federal agency. Failure to pay on time subjects the
contractor to an interest penalty owed to the subcontractor. Subcontractors
have the same obligation to pay sub–subcontractors.
8.) What is substantial completion and what are the ramifications to the owner and
contractor of the contractor achieving substantial completion?
a. Substantial completion is the point at which the project may be occupied
and used for its intended purpose. It may entitle the contractor to payment