21.15 Sampling 3 units per hour means that on average we will produce 38,500 units before
erroneously concluding that the process is out of control when it isn’t. Sampling 2 units per half
21.16 Number of units = Production
ARL = 2000(385) = 770,000
21.19 Number of units = Production
ARL = 4000(385) = 1,540,000
21.20a From Beta-mean spreadsheet,
= .3659
21.22 Sampling 10 units per half hour means that on average we will produce 770,000 units before
erroneously concluding that the process is out of control when it isn’t. Sampling 20 units per hour