17. You want to use a tool to schedule rooms and human resources courses.
18. You want to use a tool for building a new submarine.
19. You want a tool to schedule the making of eight products on six different types of machines.
B. Gantt chart. Gantt charts can show the progress of multiple products.
20. You want a tool for building a new office facility to rent out 10 units.
C. PERT network. Building an office building requires a set sequence of relatively complex activities.
21. You want a tool to develop a procedure for a new method of reporting absenteeism.
Applying the Concept 15–5: Measuring Productivity
The standard monthly productivity rate in your department is
For the first five months of the year, calculate the current productivity rate and show it as a ratio and a
percentage. Also, calculate the percentage productivity change, compared to the standard, stating
whether it is an increase or a decrease.
22. January: outputs of 5,900, inputs of $9,000
_____ ratio, _____%, increase/decrease of _____%
23. February: outputs of 6,200, inputs of $9,000
_____ ratio, _____%, increase/decrease of _____%
24. March: outputs of 6,000, inputs of $9,300
_____ ratio, _____%, increase/decrease of _____%
.65:1 ratio, 65%, increase/decrease of 2.99%
25. April: outputs of 6,300, inputs of $9,000
_____ ratio, _____%, increase/decrease of _____%
26. May: outputs of 6,300, inputs of $8,800