Case Study III-6 BAT Taiwan: Implementing SAP for a Strategic Transition
Teaching Note on Case Study III-6
BAT Taiwan: Implementing SAP for a Strategic
Transition
Objectives
multinational corporations can implement an enterprise system standard in a small country office
by leveraging IS resources and expertise housed in a regional center (here the Asia Pacific Shared
This case study therefore also gives students a better understanding of what it takes for a small
business to implement a complex enterprise system package, such as SAP R/3. The company
here is a global firm with end markets across the globe that sell tobacco products; given the recent
research on health problems associated with the usage of tobacco, the growth markets for the firm
[Note: The Shared Services unit in the Asia Pacific region that BAT Taiwan utilized is described
in a separate case study in this textbook. See Case Study IV-9: BAT-APSS: Shared Services at a
Multinational Firm.]
From consideration of this case study, students will:
Learn how an ERP system standard can be implemented in multinational corporations with
Overview
The functionality and potential benefits of enterprise resource planning systems (ERPs) are
Case Study III-6 BAT Taiwan: Implementing SAP for a Strategic Transition
are particularly challenging because of the complexity of the packages and the typical goal of
achieving a certain level of standardization across all divisions.
An ERP system such as SAP R/3 is extremely flexible and can be configured to support virtually
any business strategy and company structure. However, changes once the system is implemented
are not easy to achieve. Two extreme approaches for initially implementing an ERP system in a
global corporation are as follows:
A global ERP configuration with a single instance in a single production client. If the
operations of the corporation are sufficiently interrelated so that many of the decisions can be
made centrally (such as purchase of raw materials), or with data that are shared (such as the
Company Background and Structure
BAT is a large publicly-held company that manufactures and/or distributes cigarettes in
approximately 120 countries. With annual revenues of approximately $34 billion in 2000, it is,
today, having grown by merger and acquisition, the second largest company in the tobacco
Background on the BAT IT Function
IT function has focused on common platforms, standards, and integrated solutions, with the aim
of reducing service delivery costs. One aspect has been to focus on global strategies to help
reduce the costs of implementing integrated IT solutions and ongoing IT service delivery.
Case Study III-6 BAT Taiwan: Implementing SAP for a Strategic Transition
220
in Hong Kong.
BAT Taiwan (BATT) Background
Prior to January 2001, BAT Taiwan was a branch office of BAT U.K. responsible for marketing
arket)
trading status (and therefore its overall business model). First, when BAT merged with Rothmans
ems needs prior to the change in overall business model were provided by BAT U.K
(United Kingdom), which uses R/3. Hence Taiwan personnel were somewhat familiar with the
system that they would be using as of January 1, 2001. However, because of the limited trading
SAP R/3 Implementation Project at BATT
[Note: The key characteristics described below are based on Brown and Vessey (2003); see full
reference below.]
Organizational Characteristics
ERP Package Capabilities, Choice, and Scope
BATT wanted to use R/3 to support its new operations, so long as the system could be
implemented and supported at a cost commensurate with its small market size. Preliminary
investigations revealed the feasibility of significantly lower costs by seeking R/3 services internal
to BAT for both deployment and operations and ma
The system was to be implemented in two phases. Phase 1, which was to run from September 25,
2000, to January 2, 2001, would permit BATT to import product, while Phase 2, with an
ERP Project Critical Success Factors
1) Top management is engaged in the project, not just involved.
Mah Yong Tian was the business sponsor for the project. He initiated the study by Bain
2) Project leaders are veterans, and team members are decision makers.
The project was essentially managed by three people, one from each of the units with vested
interests in the success of the project, each of whom had distinct responsibilities. C. Y. Lee,
Case Study III-6 BAT Taiwan: Implementing SAP for a Strategic Transition
222
Two functional sub-teams were formed from APSS personnel and BATT power users as follows:
1) sales and distribution and materials management (2 APSS, 1 BATT); and 2) financials and
controlling (2 APSS and 5 BATT). Business process owners were also designated as formal
participants. However, the major business process owner role was played by H. Y. Lim, who
initially was the designated process owner for logistics and then assumed that role also for
3) Third parties fill gaps in expertise and transfer their knowledge.
implementation (see
4) Change management goes hand-in-hand with project planning.
Change management involves anticipating the effects that the new application will have on
individuals, communicating with personnel regarding the upcoming changes, defining new roles,
and providing training for those involved in using the new system. Change management
5) A satisficing mindset prevails.
Complexity in the BATT project was reduced by using an existing template, the Symphony
means that the business processes are largely determined by the template, although the system
still needs to be tailored by company code (i.e., country or end market) to reflect the specific
Case Study III-6 BAT Taiwan: Implementing SAP for a Strategic Transition
223
Adding to the complexity of the initial implementation was the schedule change that brought
forward Phase 2, due to be completed in June 30, 2001, to the same completion date as Phase 1
(January 2, 2001). This change proved troublesome for two major reasons. First, it stretched the
power users who were already performing their daily functions at the same time as working on
the project team. In response to concerns regarding system quality and adequacy of the resources
Epilogue
Although the technical system functioned extremely well in the three months following Go Live,
procedural errors due to lack of process knowledge on the part of the BATT users did cause some
initial problems. APSS has also developed a six-tier support plan as part of its help desk
capability to support the users of systems for which it is responsible. Each tier is assigned a
priority ranking and minimum service levels are specified. Knowledge regarding the Taiwan
Selected References
ches: Towards a contingency
ICIS Conference Proceedings, 1999.
MIS Quarterly Executive, 2:1 (March 2003).
Case Study III-6 BAT Taiwan: Implementing SAP for a Strategic Transition
224
Questions for Discussion
1. Why did BATT believe that implementing SAP R/3 was the best enterprise system
software package for this unit to implement?
[Note: The discussion could begin with a general discussion of the potential benefits from an ERP
syste
smaller Sage Tetra CS3.]
2. Discuss the pros and cons for BATT to use APSS personnel rather than a well-known
consultant firm for an implementation partner?
The APSS personnel were less experienced than the typical Andersen Consulting (now
3. What are some of the potential advantages associated with the usage of a BAT template
for BAT Taiwan?
4. Using the five factors associated with the success of an ERP project (in Chapter 11),
evaluate how well this initial implementation project was conducted.
This was a risky project because of the dependence on IS resources external to the BAT Taiwan
office, as well as the need to train personnel new to BATT on processes new to BATT at the same
time that the system is being implemented. However, the project met the criteria for success
Case Study III-6 BAT Taiwan: Implementing SAP for a Strategic Transition
225