Case Study III-1 Managing a Systems Development Project at Consumer and Industrial Products, Inc.
187
4. Describe the role of the project steering group.
The steering group, chaired by Anderson, was composed of the three accounts payable
supervisors whose areas were affected by the project, Shaw, and the manager of the
5. Discuss the role of IS management in the PAS project.
Henry Carter, IS supervisor of disbursements systems, was responsible for all of the systems
being developed for the disbursement department. He allocated IS staff to the various projects
and was supposed to be managing the directors of these projects.
6. Describe the role of the Stradis methodology in the PAS project. Discuss the advantages
and disadvantages of the use of the Stradis methodology in this project.
Stradis is a structured development methodology that was used for the PAS project. It divides the
development into eight phases: initial study, detailed study, draft requirements study, outline