3
C. The Mod IV team, already in its 4th year, is not working well.
During its first two years, the team was engineering-driven. Its
objective was risky and pervasive. After 2 years of pursuing
technical activities in a sequential manner, marketing was added
D. The team members are evaluated by their respective functional
line managers and not by the team managers. This performance
evaluation policy reduces the teams to working as traditional
E. Currently the status of the Mod IV team is as follows: (1)
there will likely be a delay of product introduction (i.e.,
introduction scheduled for August ‘89, manufacturing must start
3. What do you expect will in fact happen at a team meeting (to
resolve the modules issue)? (a) If you were in Linda Whitman’s
shoes, how would you feel about the team and Mod IV? (b) If you
were in Larry Rodgers’ shoes, how would you feel about the team
and Mod IV? (c) If you were in John Bailey’s shoes, how would you
feel about the team and Mod IV?
A. If I were Linda Whitman, Director of HVAC Controls with P/L
responsibility for Mod IV and marketing, my principal concerns