Chapter 17
Performance and
Discharge in Traditional
and
E-Contracts
Case 17.1
129 N.E. 889
23 A.L.R. 1429
(Cite as: 230 N.Y. 239, 129 N.E. 889)
JACOB & YOUNGS, Inc.,
v.
manufacture.’ The defendant learned in March, 1915, that some of the pipe, instead of being made in Reading, was the product of
other factories. The plaintiff was accordingly directed by the architect to do the work anew. The plumbing was then encased within
the walls except in a few places where it had to be exposed. Obedience to the order meant more than the substitution of other
pipe. It meant the demolition at great expense of substantial parts of *241 the completed structure. The plaintiff left the work
untouched, and asked for a certificate that the final payment was due. Refusal of the certificate was followed by this suit. The
resulting damage, and will not always be the breach of a condition to be followed by a forfeiture. Spence v. Ham, 163 N. Y. 220,
57 N. E. 412, 51 L. R. A. 238; Woodward v. Fuller, 80 N. Y. 312; Glacius v. Black, 67 N. Y. 563, 566; Bowen v. Kimbell, 203 Mass.
364, 370, 89 N. E. 542, 133 Am. St. Rep. 302. The distinction is akin to that between dependent and independent promises, or
between promises and conditions. Anson on Contracts (Corbin’s Ed.) s 367; 2 Williston on Contracts, s 842. Some promises are
so plainly independent that they can never *242 by fair construction be conditions of one another. Rosenthal Paper Co. v. Nat.
subject-matter, if defective, is in shape to be returned. From the conclusion that promises may not be treated as dependent to the
extent of their uttermost minutiae without a sacrifice of justice, the progress is a short one to the conclusion that they may not be so
treated without a perversion of intention. Intention not otherwise revealed may be presumed to hold in contemplation the
reasonable and probable. If something else is in view, it must not be left to implication. There will be no assumption of a purpose
to visit venial faults with oppressive retribution.
579. Where the line is to be drawn between the important and the trivial cannot be settled by a formula. ‘In the nature of the case
precise boundaries are impossible.’ 2 Williston on Contracts, s 841. The same omission may take on one aspect or another
608. There is no general license to install whatever, in the builder’s judgment, may be regarded as ‘just as good.’ Easthampton L.
& C. Co., Ltd., v. Worthington, 186 N. Y. 407, 412, 79 N. E. 323. The question is one of degree, to be answered, if there is doubt,
by the triers of the facts (Crouch v. Gutmann; Woodward v. Fuller, supra), and, if the inferences are certain, by the judges of the
law (Easthampton L. & C. Co., Ltd., v. Worthington, supra). We must weigh the purpose to be served, the desire to be gratified,
the excuse for deviation from the letter, the cruelty of enforced adherence. Then only can we tell whether literal fulfillment is to be
from cellar to roof. In point of fact, the plaintiff never reached the stage at which evidence of the extent of the allowance became
necessary. The trial court had excluded evidence that the defect was unsubstantial, and in view of that ruling there was no
occasion for the plaintiff to go farther with an offer of proof. We think, however, that the offer, if it had been made, would not of
necessity have been defective because directed to difference in value. It is true that in most cases the cost of replacement is the
measure. Spence v. Ham, supra. The owner is entitled to the money which will permit him to complete, unless the cost of
Case 17.2
C.A.7 (Wis.),2009.
Wisconsin Elec. Power Co. v. Union Pacific R. Co.
557 F.3d 504
United States Court of Appeals,
Seventh Circuit.
WISCONSIN ELECTRIC POWER COMPANY, Plaintiff-Appellant,
v.
UNION PACIFIC RAILROAD COMPANY, Defendant-Appellee.
322 CASE PRINTOUTS TO ACCOMPANY BUSINESS LAW
No. 08-2693.
Argued Jan. 7, 2009.
Decided March 2, 2009.
POSNER, Circuit Judge.
WEPCO, an electric utility that is the plaintiff in this diversity suit for breach of contract (governed by Wisconsin law), appeals from
the grant of summary judgment to the defendant, the Union Pacific railroad. The contract was for the transportation of coal to
WEPCO from coal mines in Colorado between the beginning of 1999 and the end of 2005. The appeal presents two issues:
whether a force majeure clause in the contract authorized the railroad to increase its rate for shipping the coal, and whether the
railroad breached its duty of good-faith performance of its contractual obligations by failing to ship the tonnage requested by
WEPCO on railcars supplied by the railroad.
[1] The doctrine of impossibility in the common law of contracts excuses performance when it would be unreasonably costly (and
sometimes downright impossible) for a party to carry out its contractual obligations. If the doctrine is successfully invoked, the
contract is rescinded without liability. The standard explanation for the doctrine is that nonperformance is not a breach if it is
caused by a circumstance “the nonoccurrence of which was a ‘basic assumption on which the contract was made.’
Restatement
(Second) of Contracts,
introductory note to ch. 11, preceding § 261 (1981), quoting UCC § 2-615. But this explanation leaves
unexplained why parties to a *506 contract would have assumed that a condition would not occur that has occurred. Was it just a
lack of foresight? Or is the idea behind the doctrine, rather, that the parties, had they negotiated with reference to the contingency
that has come to pass and has made performance infeasible or fearfully burdensome, would have excused performance? The
Cir.1974); 2 E. Allan Farnsworth,
Farnsworth on Contracts
§ 9.6, p. 643 (3d ed.2004)-a guess at what the parties would have
provided in their contract had they thought about the contingency that has arisen and has prevented performance or made it much
299-300 (1881); see
Field Container Corp. v. ICC,
712 F.2d 250, 257 (7th Cir.1983). The key is
binding
promise. To defeat the
application of the doctrine of impossibility the contract must state that the promisor must pay damages even if he commits a *507
breach that could not have been prevented at a reasonable cost.
Modern contracting parties often do contract around the doctrine, though not by making the promisor liable for any and every
failure to perform-rather by specifying the failures that will excuse performance. The clauses in which they do this are called force
the contract, and some of the other provisions in the article do specify contingencies that would excuse performance, including
certain “acts of God.” But the provision at issue merely provides that if the railroad is prevented by an event of Force Majeure”
from reloading its empty cars (after it has delivered coal to WEPCO) with iron ore destined for Geneva, Utah, it can charge the
higher rate that the contract makes applicable to shipments that do not involve backhauling. Cf. 2 Farnsworth,
supra,
§ 9.1, p. 585;
14
Corbin on Contracts
§ 74.19, p. 113 (Joseph M. Perillo ed.2008). For example, the rate for coal shipped from one of the
final closing the railroad wrote WEPCO to declare “an event of Force Majeure” and that henceforth it would be charging WEPCO
the higher rate applicable to shipments without a backhaul. It did not attempt to make the rate change retroactive. Had it invoked
the force majeure clause when the steel mill first shut down, WEPCO would have incurred an extra $7 million in shipping *508
charges between then and the belated declaration of force majeure.
Despite this windfall, WEPCO argues that the railroad broke the contract by invoking the force majeure clause when it did. The fact
that the railroad didn’t invoke the clause earlier shows that the shutting down of the steel mill did not prevent the railroad from
charging the low, backhaul rate. Well of course not; it is never “impossible” to offer a discount. But what the contract says is that
the railroad may charge the higher rate if it is prevented from reloading its cars, rather than if it is prevented from charging a lower
rate.
WEPCO points out that Article XI requires prompt notification of an event of force majeure and also requires the invoker to make
reasonable efforts to eliminate or abate the force majeure. It argues that the railroad violated its duty of prompt notice and by doing
so waived its right to declare a force majeure. But another clause in the contract provides that a failure of a party to insist on a right
that the contract confers on it shall not be deemed a waiver. That scotches WEPCO’s argument except insofar as it wishes to
complain not about the declaration of force majeure as such but simply about the breach of the duty of prompt notice.
A “no waiver” clause is appropriate in a complex multiyear contract that imposes (as we will see) duties of performance on both
parties, as distinct from a simple sales contract in which one party performs and the other pays. If a party lost a contract right
through waiver by failing to assert it as soon as it was violated, the process of amicable adjustment of contingencies bound to arise
in the course of performing the contract would be impeded by premature assertion of legal claims.
Monarch Coaches, Inc. v. ITT
Industrial Credit,
818 F.2d 11, 13 (7th Cir.1987);
S & R Co. of Kingston v. Latona Trucking, Inc.,
159 F.3d 80, 85-86 (2d Cir.1998);
S.H.V.C. v. Roy,
188 Conn. 503, 450 A.2d 351, 353 (1982); Sean J. Young, “Reaping the Benefits of ‘Forbearance’ in Contract
277 (7th Cir.1996);
DeValk Lincoln Mercury, Inc. v. Ford Motor Co.,
811 F.2d 326, 334 (7th Cir.1987);
Klipsch, Inc. v. WWR
Technology, Inc.,
127 F.3d 729, 735-36 (8th Cir.1997), there is still some authority for treating them as themselves waivable. E.g.,
Exxon Corp. v. Crosby-Mississippi Resources, Ltd.,
40 F.3d 1474, 1491-92 (5th Cir.1995);
Westinghouse Credit Corp. v. Shelton,
645 F.2d 869 (10th Cir.1981); but see
DeValk Lincoln Mercury, Inc. v. Ford Motor Co., supra,
811 F.2d at 334. But if that notion
were taken literally, no-waiver clauses would be worthless. Fortunately, it is not taken *509 literally; the waiver of a no-waiver
2005), which, however, for what it is worth, rules that no-waiver clauses are enforceable and does not suggest any limitations on
their enforceability.
A claim arising from breach of the prompt-notice clause might have merit were there doubt whether there really had been an event
of force majeure. The argument would be that for want of receiving prompt notice WEPCO had lost an opportunity to investigate
and discover that there was no such event. But WEPCO does not suggest that the steel mill may not really have shut down, for
good as it later turned out, in November of 2001. It does argue that if notified promptly of the shut down it might have explored
alternative ways of obtaining coal at a rate below the higher, no-backhaul rate. The contract required WEPCO to ship specified
minimum tonnages of coal by the railroad, but it shipped more, and conceivably would have shipped less-perhaps making up the
difference from some other coal mine-had it been able to find a cheaper rate from some other railroad. But there is no evidence
that such alternatives ever existed, or, more to the point, existed in 2001 but evaporated by 2004.
Not only has WEPCO failed to show any detrimental reliance on the failure to receive prompt notice of the higher rate; it refuses,
contrary to the most elementary principles of damages, to acknowledge that had it relied to its detriment any damages caused by
that reliance would have to be reduced by $7 million. That is the cost WEPCO saved as a result of the railroad’s forbearance to
invoke the force majeure clause at the earliest possible opportunity.
WEPCO argues that the railroad made no reasonable effort to abate the force majeure, as the contract required. The railroad did
not explore the possibility of finding some other commodity, besides iron ore, to ship west. (It couldn’t be iron ore, because Geneva
Steel was the only buyer of iron ore served by the railroad.) But that is not what the duty of abatement contemplated. The event of
force majeure-the event that the railroad was required to exert reasonable efforts to abate-was an event that prevented the railroad
from reloading its cars with iron ore for the trip back west.
Had Geneva Steel owed the railroad some small amount of money and begged it to forbear to sue to collect because that would
force the company into bankruptcy, forbearance to sue might conceivably be a reasonable effort to avoid the railroad’s having to
send its trains west without a backhaul, and therefore an effort that the railroad was obligated to undertake. But there is no
suggestion of that. WEPCO’s argument, rather, is that the railroad should have looked for something else to carry back in its trains.
But that would have placed on the railroad a burdensome open-ended duty to explore the possibility of reconfiguring its operations,
which would have required searching for, finding, and making contracts with other shippers and perhaps purchasing or renting
railcars optimized to carry those shippers’ commodities. Disputes over the adequacy of the railroad’s efforts would present
CHAPTER 17: PERFORMANCE AND DISCHARGE 325
Case 17.3
Tex.App.-Houston [1 Dist.],2010.
Merry Homes, Inc. v. Chi Hung Luu
S.W.3d —-, 2010 WL 547373 (Tex.App.-Hous. (1 Dist.))
Court of Appeals of Texas,
Chi Hung Luu void for illegality, since the lease only authorized the operation of a nightclub or bar at the premises and
Luu was unable to obtain a liquor license due to the premises’ proximity to a public school. The trial court awarded
Luu $6000 for the security deposit, $25,300 in attorney’s fees, and denied Merry Homes’ counterclaim for unpaid rent.
In nine issues, Merry Homes (1) challenges the legal and factual sufficiency of fifteen different findings of fact and
conclusions of law; (2) contends the trial court erred in holding the lease void for illegality, using an admission made
specialized in obtaining liquor licenses, to discuss the requirements for such a license. The representatives of Kim
Marketing informed Luu that he did not need to secure a lease before he applied for a liquor license, though Yu, as
the landlord’s representative, had to supply lease information on the license application. In December 2004, Luu
submitted a proposal of lease terms to Merry Homes, including proposed monthly rent ranging from $7000 to $7700
for a five year lease term, a security deposit of $7000, and Luu’s right to terminate the lease with forty-five days’
other” purpose. The lease also prohibits Luu from using the premises for “any activity that violates any applicable law,
regulation, zoning ordinance, restrictive covenant, [or] governmental order” or for “any activity that violates any
applicable federal, state, or local law.” An additional provision requires Luu to “satisfy [himself] that the leased
premises may be used as [Luu] intends by independently investigating all matters related to the use of the leased
premises or Property.”
After the meeting with Yu, Luu began investigating the possibility of opening a restaurant instead of a bar. Luu
testified that a restaurant required a full kitchen and thus a significantly more expensive build-out than a bar. Luu
ultimately determined that opening a restaurant instead of a bar would not be financially feasible.
Merry Homes refused to refund Luu’s deposit or cancel the lease. Luu sought a declaratory judgment that the lease
was void since it could not be performed legally, and also asserted claims of common law and statutory fraud,
Discussion
Standard of Review
In an appeal from a bench trial, the trial court’s findings of fact have the same weight as a jury verdict.
HTS Servs.,
Inc. v. Hallwood Realty Partners, L.P.,
190 S.W.3d 108, 111 (Tex.App.-Houston [1st Dist.] 2005, no pet.). We review
a trial court’s findings of fact under the same legal and factual sufficiency of the evidence standards used when
evidence if a reasonable fact-finder could do so, and disregard contrary evidence unless a reasonable fact-finder
could not.
See id.
at 827. “[F]indings of fact bind an appellate court only if the findings are supported by evidence of
probative force.”
Thomas v. Casale,
924 S.W.2d 433, 437 (Tex.App.-Fort Worth 1996, writ denied);
see also Jerry v.
Ky. Cent. Ins. Co.,
836 S.W.2d 812, 815 (Tex.App.-Houston [1st Dist.] 1992, writ denied). Anything more than a
scintilla of evidence is legally sufficient to support the fact-finding.
Formosa Plastics Corp. USA v. Presidio Eng’rs &
[1] In two issues, Merry Homes challenges thirteen findings for legal and factual sufficiency. Seven of these thirteen
findings are conclusions of law. Merry Homes challenges the following conclusions:
• Sections 9(a) and Sections 10(a)(3) and (5) are in fatal conflict;
• Luu could not perform the lease legally due to the location’s proximity to a school;
• Due to the fatal conflict and Luu’s inability to legally perform his obligations, the lease is void;
328 CASE PRINTOUTS TO ACCOMPANY BUSINESS LAW
section 13.
challenges the following findings:
• Luu reasonably and in good faith believed he could open a bar and did not learn otherwise until after he signed the
lease;
• Yu told Luu to sign the lease before he would assist with the liquor license application;
month after signing the lease, he immediately called Yu and requested a meeting to determine how to proceed.
[2] Yu testified that he never met with Luu and Dao regarding the denial of the liquor license, but Luu and Dao both
testified that they met with Yu immediately after receiving the City’s denial, and they informed him of the denial and
discussed alternative lease options. Viewing the evidence in the light most favorable to the fact-findings, we hold that
legally sufficient evidence exists to support the trial court’s findings that (1) Luu reasonably believed he could open a
some food at the bar, though it was unaware of the extent of food service. According to McGrane, if she had believed
that Luu would build a full kitchen for a restaurant, then she would not have prepared the lease to read that Luu could
use the premises to operate a nightclub or bar and for “no other” purpose. We hold that legally sufficient evidence
exists to support the trial court’s finding that the parties thought that the premises would be used for a nightclub or
bar.
review of the record indicates that the findings are not so contrary to the overwhelming weight of the evidence as to
be clearly wrong and unjust.
See Cain,
709 S.W.2d at 176. We therefore hold that factually sufficient evidence
supports the trial court’s findings of fact.
Legality of the Lease
[6][7][8] Merry Homes contends that the trial court erred in determining that the lease was void because Luu could not
ordinance existed absolutely prohibiting the performance by either or both of the parties to the contract, and no
method is therein provided whereby the contract could be performed without violation of the ordinance, then, and only
then, could the contract be held void.”). But, we must not enforce an illegal contract, “particularly where the contract
involves the doing of an act prohibited by statutes intended for the protection of the public health and welfare.”
Peniche v. Aeroméxico,
580 S.W.2d 152, 155 (Tex.Civ.App.-Houston [1st Dist.] 1979, no writ).
[10] Here, the Texas Alcoholic Beverages Code authorizes counties and cities to adopt regulations prohibiting the
sale of alcohol within 300 feet of a public school.
See
TEX. ALCO. BEV.CODE ANN.. § 109.33(a) (Vernon 2007). The
City of Houston has adopted such a regulation.
See
Houston, Tex., Code of Ordinances ch. 3, art. I, § 3-2(a) (1968).
The Texas Legislature and the City of Houston enacted this statute and ordinance, respectively, to protect the health
and safety of the general public.
See
TEX. ALCO. BEV.CODE ANN.. § 1.03 (Vernon 2007) (“This code is an exercise
trial court properly determined that this lease is void for illegality.
Merry Homes relies on
Houston Ice & Brewing Co. v. Keenan
for the proposition that Luu unconditionally bound
himself to perform under the lease, and thus the City of Houston’s refusal to grant a liquor license should not excuse
his performance, especially because the City’s denial is a contingency that Luu should have anticipated.
See
99 Tex.
79, 88 S.W. 197 (1905). The lease in
Keenan
limited the use of the premises to the operation of a saloon in Ellis
Id.
at 198. Relying on
Keenan,
Merry Homes maintains that the lease is not void for illegality because the lease
required Luu to “satisfy” himself that the premises could be used as he intended.
We agree with Luu that
Keenan,
which involves a supervening illegality after execution of the lease, is factually
distinguishable.FN1 The Dallas Court of Appeals noted that the permissible use in the
Keenan
lease was “entirely
legal” when the lease contract was executed.
Id.
Here, the City of Houston enacted the ordinance prohibiting the sale
that a lease for a purpose contrary to the
applicable zoning laws
is not a lease for an illegal purpose when the
purpose may become permissible if a license, permit, or variance is obtained.” RESTATEMENT (SECOND) OF
PROP.: LANDLORD & TENANT § 9.2 reporter’s n. 3 (1977) (emphasis added). Courts in other jurisdictions have
noted that the zoning scenario is unique since the governing authority “frequently” grants variances from zoning
regulations.
See Warshawsky v. Am. Auto. Prods. Co.,
12 Ill.App.2d 178, 138 N.E.2d 816, 819 (1956);
see also Pa.
This case, therefore, is governed by section 9.1(1) of the Restatement (Second) of Property: “If the parties to the
lease both intend that the leased property is to be used for a purpose illegal under all circumstances, the lease is
unenforceable against the tenant.” RESTATEMENT (SECOND) OF PROP.: LANDLORD & TENANT § 9.1(1);
see
also id.
§ 12.4 (stating lease is unenforceable against landlord in same situation). Because the City of Houston does
not grant variances to the application of this ordinance, the intended use of this property as a nightclub or bar “is
business. 208 Mass. 265, 94 N.E. 307 (1911). The
Gaston
court noted, however, that “[t]his business when licensed
according to the provisions of the statute is recognized by law as legal. It was possible in the nature of things lawfully
to comply with all the stipulations of the lease.”
Id.
Here, it was impossible for Luu to satisfy the requirements of the
ordinance and simultaneously comply with the terms of the lease because the lease agreement fixed the premises in
a locale where no bar or nightclub could operate.
fact of which he has no reason to know and the non-existence of which is a basic assumption on which the contract
is made, no duty to render that performance arises, unless the language or circumstances indicate the contrary.
See id.
§ 266(1). The last clause of section 266 provides that a party may agree to perform despite the existing
impracticability.
See id.
cmt. b. Comment a to section 266 notes that “the rules on agreements unenforceable on
grounds of public policy stated in Chapter 8 will also apply. To the extent that the latter bar relief for reasons based on
332 CASE PRINTOUTS TO ACCOMPANY BUSINESS LAW
(Tex. Comm’n App.1926, judgm’t adopted)) (emphasis added);
see also Centex Corp. v. Dalton,
840 S.W.2d 952, 955
(Tex.1992) (“The updated Restatement (Second) of Contracts § 261 omitted [the “no reason to anticipate”]
requirement, explaining that many factors may excuse a failure to deal with contingencies, and that even if the event
was reasonably foreseeable,
or even foreseen,
the contracting party may still be discharged.”) (emphasis added). The
[13][14] In its seventh issue, Merry Homes contends that the trial court erred in awarding attorney’s fees to Luu
because the court erroneously determined that the lease was void; therefore, the award of attorney’s fees was, as a
matter of law, neither equitable nor just. In suits brought under the Declaratory Judgment Act, attorney’s fees awards
are within “the trial court’s sound discretion, subject to the requirements that any fees awarded be reasonable and
necessary, which are matters of fact, and to the additional requirements that fees be equitable and just, which are
findings are not relevant to the issue of the lease’s enforceability and do not support the trial court’s judgment. A trial
court’s findings of fact are binding unless challenged on appeal, and we may not disregard findings of fact unless the
findings are so contrary to the overwhelming weight of the evidence as to be manifestly wrong.
El Puerto de
Liverpool v. Servi Mundo Llantero S.A. de C.V.,
82 S.W.3d 622, 628 (Tex.App.-Corpus Christi 2002, pet. dism’d
w.o.j.);
Perna v. Hogan,
162 S.W.3d 648, 656 (Tex.App.-Houston [14th Dist.] 2005, no pet.). As discussed above, we
performed legally against Merry Homes. A matter admitted pursuant to a request for admission is “conclusively
CHAPTER 17: PERFORMANCE AND DISCHARGE 333
established as to the party making the admission.” TEX.R. CIV. P. 198.3. Even without Yu’s admission, the facts
support the trial court’s conclusion that Luu could not operate a business in the leased space consistent with both the
City of Houston ordinance and the terms of the lease limiting the use of the premises exclusively to a nightclub or bar.
Merry Homes thus failed to establish that any use of this admission against Merry Homes constitutes harmful error.
See
TEX.R.APP. P. 44.1(a).
Conclusion
We hold that the trial court correctly determined that the lease was void because Luu could not perform his obligation
under the lease to avoid violating a City of Houston ordinance. We further hold that the trial court’s award of $23,500
in attorney’s fees to Luu was not inequitable or unjust. We therefore affirm the judgment of the trial court.
FN1. Even if
Keenan
is applicable to this case involving a pre-existing illegality, as opposed to a supervening
illegality, we note that the holding in
Keenan
relied heavily on the fact that Ellis County’s exercise of its option
to prohibit the sale of alcohol was highly foreseeable at the time Keenan entered into the lease agreement
FN2. Merry Homes points out that section 9.2 of the Restatement (Second) of Property, which allows a tenant
to terminate a lease if the intended use of the property later becomes illegal, begins by stating “[e]xcept to the
extent the parties to a lease validly agree otherwise,” and contends that section 10(c) of the lease brings this