9-1
CHAPTER 9
STANDARD COSTING:
A FUNCTIONAL-BASED CONTROL APPROACH
DISCUSSION QUESTIONS
1. Standard costs are essentially budgeted
amounts on a per-unit basis. Unit standards
serve as inputs in building budgets.
2. The quantity decision is determining how
much input should be used per unit of out-
put. The pricing decision determines how
much should be paid for the quantity of input
used.
3. Historical experience is often a poor choice
for establishing standards because the his-
torical amounts may include more inefficien-
cy than is desired.
4. Ideal standards are perfection standards,
representing the best possible outcomes.
Currently attainable standards are standards
that are challenging but allow for inefficien-
cy. Currently attainable standards are often
chosen because many feel they tend to mo-
tivate rather than frustrate.
5. By identifying standards and assessing de-
viations from the standards, managers can
locate areas where change or corrective be-
havior is needed.
6. Managers generally tend to have more control
over the quantity of an input used, rather than
the price paid per unit of input.
7. The materials price variance is often com-
puted at the point of purchase rather than
issuance because it provides control infor-
mation sooner. If the variance is computed
at the point of issuance and a problem is de-
tected, this problem could have been ongo-
ing for weeks or months (depending on how
long the direct materials were in inventory
before being used).
8. Disagree. A direct materials usage variance
can be caused by factors beyond the control
of the production manager (e.g., purchase of
a lower quality of direct materials than nor-
mal).
9. Disagree. Using higher-priced workers to
perform lower-skilled tasks is an example of
an event that will create a direct labor rate
variance that is controllable.
10. Inefficient direct labor, machine downtime,
bored workers, and poor quality direct mate-
rials are possible causes of an unfavorable
direct labor efficiency variance.
11. Part of a variable overhead spending vari-
ance can be caused by inefficient use of
overhead resources.
12. The volume variance is caused by the actual
volume differing from the expected volume
used to compute the predetermined standard
fixed overhead rate. If the actual volume is
different from the expected volume, then the
company has either lost or earned a contribu-
tion margin. The volume variance signals this
outcome. If the variance is large, then the
loss or gain is large since the volume vari
ance understates the effect.
13. Control limits indicate how large a variance
must be before it is judged to be material
and the process is out of control. Current
practice sets the control limits subjectively
and bases them on past experience, intui-
tion, and judgment.
14. All three approaches break the total overhead
variance into component variances. The four-
variance approach divides overhead into fixed
and variable categories (based on unit-level
behavior). It computes the variable overhead
spending and efficiency variances and the
fixed spending and volume variances. The
three-variance approach computes the
spending variance (the sum of the fixed and
variable spending variances of the four
variance approach) and the variable efficiency
and fixed overhead volume variances (same
as those of the four-variance analysis). The
two-variance analysis computes a budget var-
iance, which is the sum of the spending vari-
ances and the variable overhead efficiency
variances, and a volume variance, which is
identical to that computed using a four
variance analysis.
15. The direct materials usage and direct labor
efficiency variances can be broken into mix
and yield variances. The mix variance indi-
cates the deviation from the standard mix of
direct materials or direct labor. The yield var-
iance calculates the difference between the
actual yield and the standard yield.
CORNERSTONE EXERCISES
Cornerstone Exercise 9.1
1. Standard quarts of oil allowed:
SQ = Unit quantity standard × Actual output
2. Direct labor hours allowed:
SH = Unit labor standard × Actual output
= (24/60) × 980
3. If 970 oil changes were performed instead of 980, the standard quantities al-
Cornerstone Exercise 9.2
1. Formulas:
Materials price variance (MPV) = (AP SP)AQ = ($5.10 $5.05)6,020
2. AQ × AP AQ × SP SQ × SP
= 6,020 × $5.10 = 6,020 × $5.05 = 6,076 × $5.05
= $30,702.00 = $30,401.00 = $30,683.80
Cornerstone Exercise 9.2 (Concluded)
3. Total direct materials variance = (AP × AQ) × (SP × SQ) = MPV + MUV
= ($5.10 × 6,020) ($5.05 × 6,076)
4. If the actual quantity purchased was 6,100 quarts, the materials price variance
would be calculated at the time of purchase.
Cornerstone Exercise 9.3
1. Formulas:
Labor rate variance (LRV) = (AR SR)AH = ($14.50 $14.00)386 = $193 U
2. AH × AR AH × SR SH × SR
= 386 × $14.50 = 386 × $14 = 392 × $14
= $5,597 = $5,404 = $5,488
Cornerstone Exercise 9.3 (Concluded)
3. Total direct labor variance = (AR × AH) (SR × SH) = LRV + LEV
= ($14.50 × 386) ($14.00 × 392)
4. If the actual direct labor wage rate was $12.40 in June, the direct labor rate
variance would be:
Cornerstone Exercise 9.4
1. Variance for June = $328,000 $330,500 = $2,500 U
Variance for July = $328,000 $343,000 = $15,000 U
2. 4% of standard cost = 0.04 × $328,000 = $13,120
Cornerstone Exercise 9.5
1. Cost of Goods Sold …………………………... 25,790
Direct Materials Price Variance ………. 13,450
2. Immaterial variance account balances are in MUV and LRV. The closing entry
is:
Prime Percentage
Costs of Total
Work in Process ……………….. $165,200 12.32%
Finished Goods ………………… 126,000 9.39
Work in Process (0.1232 × $12,340) ……………. 1,520
Finished Goods (0.0939 × $12,340) …………….. 1,159
Cost of Goods Sold (0.7829 × $12,340) ……….. 9,661
Direct Labor Efficiency Variance …………… 12,340
1. Total variable overhead variance = Actual variable overhead (Variable over-
2. If production had been 129,600 units, fewer direct labor hours would have
Cornerstone Exercise 9.7
1. Variable overhead spending variance
2. Variable overhead efficiency variance = (AH SH)SVOR
3.
4. If 26,100 direct labor hours had been worked in February, the variable
overhead spending variance would be smaller, but still favorable. How-
Actual Variable
Overhead
Budgeted Variable
Overhead
Applied Variable
Overhead
Cornerstone Exercise 9.8
1. Fixed overhead spending variance
2. Volume variance = Budgeted fixed overhead Applied fixed overhead
3.
4. If 129,600 units had been produced in February, there would have been no
impact on the fixed overhead spending variance (assuming that actual fixed
Actual Fixed
Overhead
Budgeted Fixed
Overhead
Applied Fixed
Overhead
Cornerstone Exercise 9.9
1. SM = Standard mix proportion × Total actual input quantity
2. Direct Material AQ SM AQ SM SP (AQ SM)SP
Tomato sauce 700 650 50 $1.40 $ 70
3. Actual mix proportion tomato sauce = 700/2,000 = 0.35, or 35%
Actual mix proportion cheese = 840/2,000 = 0.42, or 42%
4. Tomato sauce now accounts for 35 percent (700/2,000) of the total, and
cheese accounts for only 35 percent (700/2,000). The mix variance will be
Cornerstone Exercise 9.10
1. SM = Standard mix proportion × Total actual input quantity
2. Direct Labor AQ SM AQ SM SP (AQ SM)SP
3. Actual mix proportion machine operators = 160/400 = 0.40, or 40%
4. Since both types of labor account for 50 percent of total direct labor hours,
Cornerstone Exercise 9.11
1. Using the standard mix for 16 pizzas:
2. Standard cost of the yield (SPy) = $85.40/16 pizzas yielded = $5.34 per pizza
= 0.40 × 2,000 pounds = 800 pizzas
5. If the 2,000 pounds of direct materials put into process resulted in 825 pizzas,
EXERCISES
Exercise 9.12
1. Likely coworkers: operating personnel, cost accountants, and engineers. The
operating personnel of each cost center should be involved in setting stand-
ards; they are the primary source for quantity information. The materials
2. The standard prime cost per 10-gallon batch of strawberry jam is as follows:
Strawberries (7.5 qts.a @ $0.80) ………………………. $ 6.00
Other ingredients (10 gals. @ $0.45) ……………….. 4.50
3. Joe has failed to provide decision support information and recommendations
that are accurate, clear, concise, and timely; avoid apparent conflicts of inter-
Exercise 9.13
1. SQ = 8.45 lbs. × 280,000 = 2,366,000 pounds
Exercise 9.14
1. MPV = (AP SP)AQ
MPV = ($0.21 $0.20)901,200 = $9,012 U
Materials Price
Variance
$9,012 U
Materials Usage
Variance
$60 U
2. LRV = (AR SR)AH
LRV = ($17.30 $18.00)11,300 = $7,910 F
LEV = (AH SH*)SR
Labor Rate
Variance
$7,910 F
Labor Efficiency
Variance
$2,520 F
3. Materials ……………………………………………. 180,240
Direct Materials Price Variance……………. 9,012
Accounts Payable ………………………….. 189,252
AP × AQ
= $0.21 × 901,200
= $189,252
SP × AQ
= $0.20 × 901,200
= $180,240
SP × SQ
= $0.20 × 900,900
= $180,180
AR × AH
= $17.30 × 11,300
= $195,490
SR × AH
= $18 × 11,300
= $203,400
SR × SH
= $18 × 11,440
= $205,920
Exercise 9.15
1. Fixed overhead analysis:
2. Variable overhead analysis:
Actual Fixed
Overhead
= $556,250
Budgeted Fixed
Overhead
= $556,800
Applied Fixed
Overhead
SFOR × SH
= $1.16 × (4 × 119,400)
= $554,016
Actual Variable
Overhead
= $230,600
Budgeted Variable
Overhead
SVOR × AH
Applied Variable
Overhead
SVOR × SH
Exercise 9.15 (Concluded)
The variable overhead spending variance can occur because of changes
in the prices of the individual items that make up variable overhead. In this
sense, it is similar to the direct materials and direct labor price variances.
Exercise 9.16
1. Two-variance analysis:
Actual Overhead
Budgeted Overhead
Applied Overhead
Exercise 9.16 (Concluded)
2. Three-variance analysis (BFOH = Budgeted fixed overhead; OH = Overhead):
3. Two-variance: The volume variance is the same. The budgeted variance is the
sum of the fixed and variable spending variances and the efficiency variance.
Exercise 9.17
2. SPy = $324,005.20/720 = $450.01
3. Direct materials yield variance = (Standard yield Actual yield)SPy
4. Direct Material AQ SM AQ SM SP (AQ SM)SP
Actual OH
BFOH + (SVOR × AH)
BFOH + (SVOR × SH)
(SFOH + SVOR) × SH
Exercise 9.18
1. MPV = (AP SP)AQ
Solvent mix:
MPV = ($5.20 $5.27)945 = $66.15 F
Aromatic compounds:
MPV = ($8,010 $8,000)55 = $550.00 U
Solvent mix:
Materials ……………………………………….. 4,980.15
2. Materials usage variance:
AQ SQ* AQ SQ SP (AQ SQ)SP
945 928.89 16.11 $ 5.27 $ 84.90
Solvent mix:
Work in Process ……………………………. 4,895.25
Direct Materials Usage Variance …….. 84.90
Materials…………………………………… 4,980.15
Aromatic compounds:
Exercise 9.18 (Concluded)
3. The direct materials price and usage variances are both favorable and unfa-
vorable. Reasons for price variances: random market fluctuation of the input
prices, permanent changes in the input prices, changes in suppliers, quality
Exercise 9.19
1. Yield ratio = 25 units/5 hours = 5
3. Direct labor yield variance = (Standard yield Actual yield)SPy
= (325,000 320,000)$3.04 = $15,200 U
4. Direct Labor Type AH SM AH SM SP (AH SM)SP
Fabricating …………………. 20,000 26,000* (6,000) $ 20 $(120,000)
Exercise 9.20
1. MPV = (AP SP)AQ
MPV = ($0.38 $0.40)135,700 = $2,714 F
2. LRV = (AR SR)AH
LRV = ($12.10 $12.00)91,000 = $9,100 U
LEV = (AH SH)SR
3. Materials ……………………………………………. 54,280
Direct Materials Price Variance ………. 2,714
Accounts Payable ………………………….. 51,566
Exercise 9.20 (Concluded)
Exercise 9.21
1. Cases needing investigation:
3. Production engineering is responsible. If the relationship is expected to per-
sist, then the new direct labor method should be abandoned. If the favorable
Exercise 9.22
1. Fixed overhead analysis:
Actual Fixed
Overhead
Budgeted Fixed
Overhead
Applied Fixed Overhead
SFOR × SH
Exercise 9.22 (Concluded)
2. Variable overhead analysis:
3. Journal entries:
a. Work in Process …………………………………….. 675,000
Variable Overhead Control …………………. 405,000
Fixed Overhead Control……………………… 270,000
b. Variable Overhead Control ……………………… 505,300
Fixed Overhead Control ………………………….. 294,700
Miscellaneous Accounts ……………………. 800,000
Actual Variable
Overhead
= $505,300
Budgeted Variable
Overhead
SVOR × AH
= $2.25 × 190,000
= $427,500
Applied Variable
Overhead
SVOR × SH
= $2.25 × 0.20 × 900,000
= $405,000