1.
Value-added time (minutes):
Stamping
Appliance assembly
Time to test one unit
Pack and label
Total
Non-value-added time (minutes):
Wait time:
Within-batch wait time – stamping
Within-batch wait time – final assembly
Within-batch wait time – testing
Within batch wait time – shipping
Stamping setup
Total wait time
Move time:
Move from stamping to final assembly
Move from final assembly to testing
Total move time
Total non-value-added time
Total lead time (minutes)
Value-Added Time / Total Time = Value-Added Ratio
Answers are entered in the cells with gray backgrounds.
Cells with non-gray backgrounds are protected and cannot be edited.
An asterisk (*) will appear to the right of an incorrect entry. The essay answer will not be graded.
Value-added time (minutes):
Stamping 5
Non-value-added time (minutes):
Wait time:
Within-batch wait time – stamping 195
Cells with non-gray backgrounds are protected and cannot be edited.
Answers are entered in the cells with gray backgrounds.