Weygandt, Accounting Principles, 12e,
Chapter Twenty Five
Solutions to Challenge Exercises
Solution
CE25-1
(a)
Anders Painting Service
Variance Report – Purchasing Department
For the month ended XX
Actual
Gallons Actual Standard Price
Project Purchased Price Price__ Variance Explanation
Arrow Building 3,750 $76.00 $80.00 $15,000 F Poor quality paint purchased/cheaper
(b)
Anders Painting Service
Variance Report – Production Department
For the month ended XX
Actual Standard Standard Quantity
Project Gallons Gallons Price__ Variance Explanation
Arrow Building 3,750 3,500 $80.00 $20,000 U Poor quality paint/needed more
(c) Part 1:
Anders Painting Service
Variance Report – Purchasing Department
For the month ended XX
Actual
Gallons Actual Standard Price
Project Purchased Price Price__ Variance Explanation
Arrow Building 3,650 $78.50 $80.00 $ 5,475 F Paint cheaper than standard cost