An asterisk (*) will appear to the right of an incorrect entry. The essay answer will not be graded.
1.
Customer Project Engineering
Service Bidding Support
Activity cost
Activity base
serv. reqs. bids desgn. chngs.
Activity rate /serv. req. /bid /change
2.
Number Activity
of Activities Rate = Total
Gough Industries
Customer service serv. reqs. /req.
Project bidding bids /bid
Engineering support desgn. chngs. /chng.
Total nonmanufacturing activity costs
Breen Inc.
Customer service serv. reqs. /req.
Project bidding bids /bid
Engineering support desgn. chngs. /chng.
Total nonmanufacturing activity costs
3.
The
Gough Martin
Industries Breen Inc. Group
Revenues
Cost of goods sold
Gross profit
Selling and administrative activities:
Customer service
Project bidding
4.
0%
[Key code here]
Answers are entered in the cells with gray backgrounds.
Problem 18(4)-5A
Name:
Section:
Score:
Key Code:
Instructions
Cells with non-gray backgrounds are protected and cannot be edited.
[Key essay answer here]
An asterisk (*) will appear to the right of an incorrect entry. The essay answer will not be graded.
1.
Customer Project Engineering
Service Bidding Support
2.
Number Activity
of Activities Rate = Total
Total nonmanufacturing activity costs 39,800$
Total nonmanufacturing activity costs 47,150$
Total nonmanufacturing activity costs 139,300$
3.
The
Gough Martin
Industries Breen Inc. Group
4.
Problem 18(4)-5A
Name:
Solution
Section:
Cells with non-gray backgrounds are protected and cannot be edited.
Score:
Instructions
Answers are entered in the cells with gray backgrounds.
ON
The Martin Group is unprofitable, while the other two customers have acceptable margins. This is because The Martin Group requires many