Inventory in process, September 1 (c)
To complete inventory in process, September 1 (c)
Cost of completed Sept. 1 work in process
Started and completed in September (c)
Transferred to finished goods in September (c)
Inventory in process, September 30 (d)
Total costs assigned by the Rolling Department
2.
UNITS
Whole Units Direct Materials Conversion
Units charged to production:
Inventory in process, October 1
Received from Smelting Department
Total units accounted for by the Rolling Department
Units to be assigned cost:
Inventory in process, October 1 ( complete )
Started and completed in October
Transferred to finished goods in October
Inventory in process, October 31 ( complete )
Total units to be assigned cost
COSTS
Direct Materials Conversion Total
Costs per equivalent unit:
Total costs for October in Rolling Department
Total equivalent units
Cost per equivalent unit (b)
Costs assigned to production:
Inventory in process, October 1
Costs incurred in October
Total costs accounted for by the Rolling Department
Costs allocated to completed and partially completed units:
Inventory in process, October 1 (c)
To complete inventory in process, October 1 (c)
Started and completed in October (c)
Transferred to finished goods in October (c)
Inventory in process, October 31 (d)
Pittsburgh Aluminum Company
Cost of Production Report – Rolling Department
For the Month Ended October 31