CE 11-1 (continued)
(c)
Part 2: Anders Painting Service
Variance Report – Production Department
For the month ended XX
Actual Standard Standard Quantity
Project Gallons Gallons Price__ Variance Explanation
Arrow Building 3,650 3,500 $80.00 $12,000 U Average quality paint/needed more
Besler Building 3,800 4,000 $80.00 16,000 F Average quality paint/needed less
Part 3:
The change to the new supplier appears to be beneficial. Both the overall price variance and
quantity variance have improved. Further investigation would still be required into the quantity
variances for the Arrow Building and Cartwright Building projects.
Solution
CE 11-2
(a) 1.25 hours + .05 (1.25 hours) + .15 (1.25 hours) = 1.25 + .0625 + .1875 = 1.5 hours
(b) $50 + .12($50) + .20($50) = $50 + $6 + $10 = $66 per hour
(e) (1) (AQ x AP) – (AQ x SP) = Direct labor price variance
(80 pianos x 1.75 hours/piano x $62.25) – (80 pianos x 1.75 hours/piano x $66) =
$8,715 – $9,240 = $525 Favorable