A-7
P-1
A B C D E
1 SEABURY, INC.
2 Factory Overhead Cost Variance Report—Assembly Department
3 For the Month Ended October 31
4 Normal capacity for the month 25,000 hrs.
5 Actual production for the month 23,500 hrs.
6
7 Budget
8 (at Actual Variances
9 Actual Production) Unfavorable Favorable
10 Variable factory overhead costs:*
16 Supervisory salaries $125,000 $125,000
17 Depreciation of plant and
equipment 49,000 49,000
18 Insurance and property taxes 29,750 29,750
19 Total fixed cost $203,750 $203,750
20 Total factory overhead cost $388,070 $388,460
21 Total controllable variances $870 $ (1260)
*The budgeted variable costs are determined by multiplying the budgeted variable
costs per unit at planned production times the actual production for October. The
budgeted variable costs per unit are determined by dividing the budgeted variable
cost for October by the planned production for October. Thus, the budgeted
variable costs are determined as follows: