Now, we proceed to use the OPM:
V = $67.83[N(d1)] – $70e-(0.06)(1)[N(d2)].
d1 =
5.0
)1(
5.0
)142(.
)15)](0.142/206.0[()$67.83/$70ln(
= 0.2641.
d2 = d1 – (0.142)0.5(1)0.5 = 0.2641 – 0.3768
= -0.1127.
N(d1) = N(0.2641) = 0.6041.
g. Now suppose the cost of the project is $75 million and the project cannot be
delayed. But if Tropical Sweets implements the project, then Tropical Sweets
will have a growth option. It will have the opportunity to replicate the original
project at the end of its life. What is the total expected NPV of the two projects
if both are implemented?
NPV = NPV Of Original Project + NPV Of Replication Project
= -$0.39 + -$0.39/(1+0.10)3
= -$0.39 + -$0.30 = -$0.69.
Still looks like a loser, but you will only implement project 2 if demand is high. We
might have chosen to discount the cost of the replication project at the risk-free rate,