978-1285770178 Case Printout Case CPC-04-09 Part 2

subject Type Homework Help
subject Pages 11
subject Words 2948
subject Authors Roger LeRoy Miller

Unlock document.

This document is partially blurred.
Unlock all pages and 1 million more documents.
Get Access
page-pf1
support the District Court's determination that his billing was the correct amount
due for the additional services provided.
page-pf2
Lambert, 249 Mont. 455, 462, 817 P.2d 219, 223 (1991) (Court committed
reversible error when it allowed the defendant to solicit undisclosed expert
testimony from a witness previously called to discuss factual issues, when
¶ 18, 49 P.3d 565, ¶ 18 (citing Babcock, 157 Mont. at 92, 482 P.2d at 1020).
[18] Link to KeyCite Notes ¶ 37 However, such concerns about prejudicial
impact are not evident under the circumstances here. Lyons was not only the
contractor who had performed the work, he was also the party being sued. It was
obvious that he would testify regarding the extent and quality of his own work.
¶ 38 We conclude that the District Court did not abuse its discretion in permitting
Lyons to give opinion testimony concerning the quality of his own workmanship
and the reasons for the lower quality of work on this project.
¶ 39 (5) Did the District Court err by concluding that Lyons had standing to file his
construction lien and counterclaim?
be a valid lien claimant. The District Court further ruled that any relief awarded to
Weimar would be enforceable against any of the Lyons entities and individuals.
After trial, the court concluded that “Defendants Mike Lyons and Lyons Concrete,
Inc.,” were entitled to judgment on the lien.
¶ 41 Weimar argues that because the lien was recorded and sought to be
state under such name.” Thus, Weimar reasons that, because Lyons Concrete,
Inc., was not registered, and “Mike Lyons, individually,” was not named on the
lien as a claimant, neither Lyons Concrete, Inc., nor Mike Lyons were valid lien
page-pf3
claimants and the construction lien was void ab initio and unenforceable. Further,
he asserts that Lyons' counterclaim was similarly afflicted. We disagree.
construed so as to give effect to their remedial character.” General Elec. Supply
Co., Etc. v. Bennett, 192 Mont. 110, 113-14, 626 P.2d 844, 846 (1981) (citations
omitted).
FN2. Now known as a “construction lien.” See § 71-3-521 et seq., MCA.
¶ 43 Weimar challenges none of the procedures employed by Lyons, only the
admonition that the lien statute “must be interpreted liberally to protect the right of
the lien.” Kosena, 195 Mont. at 22, 635 P.2d at 1293.
[20] Link to KeyCite Notes ¶ 44 Likewise, it is clear in this case that Mike Lyons
was listed individually as a lien claimant. The lien adequately identified Mike
Lyons and imparted notice to Weimar of Mike Lyons' status as a lien claimant.
[21] Link to KeyCite Notes[22] Link to KeyCite Notes[23] Link to KeyCite Notes ¶
45 Regarding Lyons Concrete, Inc., the District Court concluded that the
corporation was likewise a valid lien claimant and entitled to judgment “under the
doctrine of Corporation by Estoppel.” Weimar acknowledges this equitable
doctrine, but argues that its application here makes no sense because a
the issue as to whether or not the corporation is validly incorporated.
“In short, the fact that an entity is not a corporation FN3 should not, in and of
itself, be a defense to an otherwise valid obligation.” General Comments to § 35-
1-119, MCA. We applied this doctrine in Valley Victory Church v. Sandon:
page-pf4
FN3. Including, according to the General Comments, an entity “whose certificate
P.2d 1109, 1112. The doctrine may apply to the corporation itself, or to the
corporation's opponent. Compare Ohaco Sheep Co., Inc. v. Heirs of Ohaco
(Ariz.App.1986), [148 Ariz. 142,] 713 P.2d 343, 346 (applying doctrine to
stockholders or partners of the purported corporation); with Lettinga v. Agristor
Credit Corp. (6th Cir.1982), 686 F.2d 442, 446 (“A person or entity who has
application here. In support of his motion for partial summary judgment on this
issue, Lyons filed an affidavit averring that he was unaware of the involuntary
dissolution of Lyons Concrete, Inc., that he continuously acted in good faith as a
corporation until he was made aware of the dissolution, and that he filed new
articles of incorporation under the same name of Lyons Concrete, Inc.,
acted in good faith through its principals, had been involuntarily dissolved.
Weimar is estopped from denying the corporate status of Lyons Concrete, Inc.,
and, with that conclusion, it was not necessary for Lyons Concrete, Inc., to
register as an assumed business name under § 30-13-215, MCA. Lastly, we are
confident that Lyons will devise a solution to the practical issue of whom Weimar
motion, forbidding Weimar from contesting the applicability of the statute to his
contract with Lyons, both as a discovery sanction for Weimar's failing to answer
discovery and upon Weimar's admission that the total cost of the construction
work on Weimar's property exceeded $400,000.FN4 Thus, the District Court, in
its findings of fact, conclusions of law and judgment, concluded that, pursuant to
page-pf5
FN5. Section 28-2-2104(1), MCA, provides: “If a periodic or final payment that is
required by a construction contract to be paid by an owner to a contractor is
delayed by more than 30 days from the date the payment is required by the
contract to be made, the owner shall pay to the contractor interest ... at the rate
of 1.5% a month....”
notice provision at any time prior to or during the trial, instead raising it for the
first time in his post-trial motion to alter or amend, and at that point there was no
evidence in the record from which the notice issue could be determined. As such,
we agree with Lyons that Weimar waived his right to contest the lack of notice.
The interest statute had been raised prior to trial by Lyons and was the subject of
in concluding that Lyons was entitled to recover interest under these statutory
provisions, because Weimar's contract with Lyons did not call for construction
work valued greater than $400,000. Weimar does not dispute that all of the
improvements to his property totaled more than $400,000, but he argues this
interest provision only applies when an individual contract costs that much.
is imposed upon “a periodic or final payment that is required by a construction
contract to be paid by an owner to a contractor....” Section 28-2-2104(1), MCA.
“Construction contract” is defined as “a written agreement FN6 between an
owner and a contractor for the contractor to construct or improve” real property.
Section 28-2-2101(1), MCA. In turn, “improvement” means “all or a part of a
page-pf6
$400,000.” Section 28-2-2107, MCA. From a plain reading of these provisions,
we conclude that the exception applies to a construction contract between an
owner and contractor for an improvement to residential real property with a total
cost of less than $400,000. Clearly, Weimar's contract with Lyons was for less
than $400,000, and, therefore, this interest statute did not apply. Other interest
sanction for discovery abuse. While a sanction may have been appropriate for
the discovery error, Weimar should not have to bear the penalty of an interest
assessment under a statute which, as a matter of law, did not apply to his
contract, and that assessment is reversed. Upon remand, if Lyons yet clamors for
imposition of a discovery sanction that matter may be brought to the attention of
consistent herewith.
Lambert, 249 Mont. 455, 462, 817 P.2d 219, 223 (1991) (Court committed
reversible error when it allowed the defendant to solicit undisclosed expert
testimony from a witness previously called to discuss factual issues, when
¶ 18, 49 P.3d 565, ¶ 18 (citing Babcock, 157 Mont. at 92, 482 P.2d at 1020).
[18] Link to KeyCite Notes ¶ 37 However, such concerns about prejudicial
impact are not evident under the circumstances here. Lyons was not only the
contractor who had performed the work, he was also the party being sued. It was
obvious that he would testify regarding the extent and quality of his own work.
¶ 38 We conclude that the District Court did not abuse its discretion in permitting
Lyons to give opinion testimony concerning the quality of his own workmanship
and the reasons for the lower quality of work on this project.
¶ 39 (5) Did the District Court err by concluding that Lyons had standing to file his
construction lien and counterclaim?
be a valid lien claimant. The District Court further ruled that any relief awarded to
Weimar would be enforceable against any of the Lyons entities and individuals.
After trial, the court concluded that “Defendants Mike Lyons and Lyons Concrete,
Inc.,” were entitled to judgment on the lien.
¶ 41 Weimar argues that because the lien was recorded and sought to be
state under such name.” Thus, Weimar reasons that, because Lyons Concrete,
Inc., was not registered, and “Mike Lyons, individually,” was not named on the
lien as a claimant, neither Lyons Concrete, Inc., nor Mike Lyons were valid lien
claimants and the construction lien was void ab initio and unenforceable. Further,
he asserts that Lyons' counterclaim was similarly afflicted. We disagree.
construed so as to give effect to their remedial character.” General Elec. Supply
Co., Etc. v. Bennett, 192 Mont. 110, 113-14, 626 P.2d 844, 846 (1981) (citations
omitted).
FN2. Now known as a “construction lien.” See § 71-3-521 et seq., MCA.
¶ 43 Weimar challenges none of the procedures employed by Lyons, only the
admonition that the lien statute “must be interpreted liberally to protect the right of
the lien.” Kosena, 195 Mont. at 22, 635 P.2d at 1293.
[20] Link to KeyCite Notes ¶ 44 Likewise, it is clear in this case that Mike Lyons
was listed individually as a lien claimant. The lien adequately identified Mike
Lyons and imparted notice to Weimar of Mike Lyons' status as a lien claimant.
[21] Link to KeyCite Notes[22] Link to KeyCite Notes[23] Link to KeyCite Notes ¶
45 Regarding Lyons Concrete, Inc., the District Court concluded that the
corporation was likewise a valid lien claimant and entitled to judgment “under the
doctrine of Corporation by Estoppel.” Weimar acknowledges this equitable
doctrine, but argues that its application here makes no sense because a
the issue as to whether or not the corporation is validly incorporated.
“In short, the fact that an entity is not a corporation FN3 should not, in and of
itself, be a defense to an otherwise valid obligation.” General Comments to § 35-
1-119, MCA. We applied this doctrine in Valley Victory Church v. Sandon:
FN3. Including, according to the General Comments, an entity “whose certificate
P.2d 1109, 1112. The doctrine may apply to the corporation itself, or to the
corporation's opponent. Compare Ohaco Sheep Co., Inc. v. Heirs of Ohaco
(Ariz.App.1986), [148 Ariz. 142,] 713 P.2d 343, 346 (applying doctrine to
stockholders or partners of the purported corporation); with Lettinga v. Agristor
Credit Corp. (6th Cir.1982), 686 F.2d 442, 446 (“A person or entity who has
application here. In support of his motion for partial summary judgment on this
issue, Lyons filed an affidavit averring that he was unaware of the involuntary
dissolution of Lyons Concrete, Inc., that he continuously acted in good faith as a
corporation until he was made aware of the dissolution, and that he filed new
articles of incorporation under the same name of Lyons Concrete, Inc.,
acted in good faith through its principals, had been involuntarily dissolved.
Weimar is estopped from denying the corporate status of Lyons Concrete, Inc.,
and, with that conclusion, it was not necessary for Lyons Concrete, Inc., to
register as an assumed business name under § 30-13-215, MCA. Lastly, we are
confident that Lyons will devise a solution to the practical issue of whom Weimar
motion, forbidding Weimar from contesting the applicability of the statute to his
contract with Lyons, both as a discovery sanction for Weimar's failing to answer
discovery and upon Weimar's admission that the total cost of the construction
work on Weimar's property exceeded $400,000.FN4 Thus, the District Court, in
its findings of fact, conclusions of law and judgment, concluded that, pursuant to
FN5. Section 28-2-2104(1), MCA, provides: “If a periodic or final payment that is
required by a construction contract to be paid by an owner to a contractor is
delayed by more than 30 days from the date the payment is required by the
contract to be made, the owner shall pay to the contractor interest ... at the rate
of 1.5% a month....”
notice provision at any time prior to or during the trial, instead raising it for the
first time in his post-trial motion to alter or amend, and at that point there was no
evidence in the record from which the notice issue could be determined. As such,
we agree with Lyons that Weimar waived his right to contest the lack of notice.
The interest statute had been raised prior to trial by Lyons and was the subject of
in concluding that Lyons was entitled to recover interest under these statutory
provisions, because Weimar's contract with Lyons did not call for construction
work valued greater than $400,000. Weimar does not dispute that all of the
improvements to his property totaled more than $400,000, but he argues this
interest provision only applies when an individual contract costs that much.
is imposed upon “a periodic or final payment that is required by a construction
contract to be paid by an owner to a contractor....” Section 28-2-2104(1), MCA.
“Construction contract” is defined as “a written agreement FN6 between an
owner and a contractor for the contractor to construct or improve” real property.
Section 28-2-2101(1), MCA. In turn, “improvement” means “all or a part of a
$400,000.” Section 28-2-2107, MCA. From a plain reading of these provisions,
we conclude that the exception applies to a construction contract between an
owner and contractor for an improvement to residential real property with a total
cost of less than $400,000. Clearly, Weimar's contract with Lyons was for less
than $400,000, and, therefore, this interest statute did not apply. Other interest
sanction for discovery abuse. While a sanction may have been appropriate for
the discovery error, Weimar should not have to bear the penalty of an interest
assessment under a statute which, as a matter of law, did not apply to his
contract, and that assessment is reversed. Upon remand, if Lyons yet clamors for
imposition of a discovery sanction that matter may be brought to the attention of
consistent herewith.

Trusted by Thousands of
Students

Here are what students say about us.

Copyright ©2022 All rights reserved. | CoursePaper is not sponsored or endorsed by any college or university.